EXECUTIVE SUMMARY
4.
Summary of Complaints, Notification
of Summons and Prosecutions
7.
Conclusion and Recommendations
List of Appendices
A. Alignment and
Works Area for the Contract No. HY/2014/08
B. Construction
Programme
C. Project
Organization Chart
D. Dust Event-Action
Plan (EAP)
E. Noise
Event-Action Plan (EAP)
F. Environmental
Mitigation Implementation Schedule (EMIS)
G. Monitoring Schedules of the Reporting Month
H. Calibration Certificate (Air Monitoring)
I. Calibration Certificate (Noise)
J. The Certification of Laboratory with HOKLAS Accredited
Analytical Tests
K. Location Plan of Noise and Air Quality Monitoring Station
L. Monitoring Data (Air Monitoring)
M.
Monitoring Data (Noise)
N. Waste Flow Table
O. Statistics on Complaint, Notifications of Summons
and Successful Prosecutions
P. Monitoring Schedule of the Coming Month
Q. Interim Report for the Complaint
Executive
Summary
A.1
Build
King – SK ecoplant Joint Venture (“Contractor”) commenced the construction
works of Highway Department (HyD) Central Kowloon Route Contract No. HY/2014/08
– Section of Yau Ma Tei East (“The Project”) on 20 April 2018. This is the 102nd
monthly Environmental Monitoring and Audit (EM&A) report presenting the
EM&A works carried out during the period from 01 September 2026 to 30
September 2026.
A.2
A
summary of the construction works reported by Main Contractor for the Project
during the reporting month is listed below.
|
Construction
Activities undertaken |
|
l Remaining drainage,
utilities and reinstatement works at Ferry Street and Yan Cheung Road. l GRF Bridge Works –
Continue rectification of defects and other associated works. l Works at Zone 1 Noise
Enclosure – Continue installation of PMMA panels and absorptive panels and
cable brackets for linear heat detection cables and laying of lighting
cables. l Works at Zone 3 Noise Enclosure – F02 - Continue
installation of cable brackets for linear heat detection cables, lighting
cables, cable containments and light fittings, brackets, trunking and copper
pipe. C07 Noise Enclosure – Continue installation of steel tie beams and main
beams. l Works at Zone 2 Noise Enclosure – Continue
installation of main beams, secondary tie beams, smoke ventilators,
absorptive panels and PMMA panels. |
A.3
A
summary of regular construction noise and construction dust monitoring
activities in this reporting period is listed below:
Regular construction noise
monitoring during normal working hours
|
W-N1A, W-P11, W-N18, W-N25A |
6 times |
Construction dust (24-hour TSP)
monitoring
|
W-A1 W-A6 |
6 times 6 times |
|
|
|
Construction dust (1-hour TSP)
monitoring
|
W-A1, W-A6 |
18 times |
A.4
Bi-weekly
inspections of the implementation of landscape and visual mitigation measures
were conducted on 10 and 24 September 2026. Details of the audit findings and
implementation status are presented in Section 5.
A.5
Joint
weekly site inspections were conducted by representatives of the Environmental
Team (ET), Contractor and Engineer on 03, 10, 17 and 24 September 2026. One
joint site inspection with IEC was also undertaken on 10 September 2026. Details
of the audit findings and implementation status are presented in Section 5.
A.6
Details
of waste management are presented in Section 3.
A.7
One Action Level
of construction noise was triggered during the reporting month as one
documented complaint regarding noise was received. No exceedance of Limit Level
of construction noise was recorded in the reporting month. No exceedance of the
Action and Limit Level of 24-hour TSP and 1-hour TSP was recorded in the
reporting month.
A.8
One
environmental complaint was received in the reporting month. After
investigation with the Contractor, precautionary measures had been proposed to
the Contractor by ET. The interim reports for the complaints are shown in
Appendix Q.
A.9
No
non-compliance was reported in the reporting month.
A.10
No
notification of summon or prosecution was received in this reporting month.
A.11
A
summary of the construction activities provided by Main Contractor in the next reporting
month is listed below:
|
Construction Activities to be undertaken |
|
l Continuing
works on remaining drainage, utilities and reinstatement works at Ferry
Street and Yan Cheung Road l GRF
Bridge Works – Continue rectification of defects and other associated works l Works
at Zone 3 Noise Enclosure –Continue E&M works at F02. For C07 Noise
Enclosure – Continue installation of steel tie beams, absorptive panels, PMMA
panels and flashing. l Works
at Zone 2 Noise Enclosure – Continue installation of absorptive panels,
infill PMMA, flashings (Smoke vent system) and E&M works. l Works
at Zone 1 Noise Enclosure –Continue flashing works and E&M works and
continue steel works for NE (V08). l Noise
Enclosure steelworks fabrication at the yard in Zhuhai, China. l Monitoring
of settlement instrumentation for areas at YMT Police Station and Prosperous
Garden |
The Central Kowloon Route – Design and Construction
Environmental Impact Assessment Report (Register No.: AEIAR-171/2013) was
approved with conditions by the Environmental Protection Department (EPD) on 11
July 2013. An Environmental Permit (EP 457/2013) was issued on 9 August 2013.
Variations of EP (VEP) was applied for and the EP (EP-457/2013/C) was issued by
EPD on 16 January 2017. Variations of EP (VEP) was subsequently applied for and
the latest EP (EP-457/2013/D) was issued by EPD on 15 June 2021. A Further EP (FEP-03/457/2013/D) was issued by EPD on
5 November 2021.
The construction of the CKR had been divided into
different sections. This Contract No. HY/2014/08 – Section of Yau Ma Tei East
(YMTE) covers part of the construction activities located
at Yau Ma Tei under the EP and FEP which includes:
Section of Yau Ma
Tei East
i.
Construction of Cut-and-Cover Tunnel in compliance with all statutory
requirements and the requirements specified under the Contract while
maintaining the traffic with all necessary provisions
ii.
Construction and subsequent handover of Yau Ma Tei Access Shaft for
facilitating the access and use by the contractor of Central Kowloon Route -
Central Tunnel contract
iii.
Demolition of existing buildings including Yau Ma Tei Multi-storey
Carpark Building, Yau Ma Tei Specialist Clinic Extension Building and Yau Ma
Tei Jade Hawker Bazaars
iv.
Demolition and re-provisioning of Gascoigne Road Flyover and the
underpinning works for the existing Ferry Street Flyover and Yau Ma Tei Police
Station New Wing Building
v.
Construction of civil provisions and coordination with the contractor of
Central Kowloon Route - Tunnel Electrical & Mechanical contract
vi.
Design and construction of Noise Barrier Works
vii.
Prepare temporary traffic arrangement proposals, discuss at Traffic
Management Liaison Group meeting and obtain its agreement and approval/
endorsement from relevant authorities at suitable times to enable the execution
of the Works
The alignment and
works area for the Contract No. HY/2014/08 - are shown in Appendix A.
A summary of the
major construction activities undertaken in this reporting period is shown in
Table 1.1. The construction programme is presented in
Appendix B.
Table 1.1 Summary of the
Construction Activities reported by Main Contractor during the Reporting Month
|
l Remaining drainage,
utilities and reinstatement works at Ferry Street and Yan Cheung Road. l GRF Bridge Works –
Continue rectification of defects and other associated works. l Works at Zone 1 Noise
Enclosure – Continue installation of PMMA panels and absorptive panels and
cable brackets for linear heat detection cables and laying of lighting
cables. l Works at Zone 3 Noise Enclosure – F02 - Continue
installation of cable brackets for linear heat detection cables, lighting
cables, cable containments and light fittings, brackets, trunking and copper
pipe. C07 Noise Enclosure – Continue installation of steel tie beams and main
beams. l Works at Zone 2 Noise Enclosure – Continue
installation of main beams, secondary tie beams, smoke ventilators,
absorptive panels and PMMA panels. |
|
|
The project
organisational chart specifying management structure and contact details are
shown in Appendix C.
A summary of the valid permits, licences, and /or
notifications on environmental protection for this Project is presented in
Table 1.2.
Table 1.2 Summary
of the Status of Valid Environmental Licence
Notification,
Permit and Documentations
|
Permit/ Licences/ Notification /Reference No. |
Valid Period |
Status |
Remark |
|
|
From |
To |
|||
|
Environmental Permit |
||||
|
EP-457/2013/D |
15 Jun 2021 |
End of Project |
Valid |
- |
|
Further Environmental Permit |
||||
|
FEP-03/457/2013/D |
5 Nov 2021 |
End of Project |
Valid |
|
|
Wastewater Discharge License |
||||
|
WT00045552-2024 |
21 Nov 2024 |
30 Nov 2029 |
Valid |
- |
|
Notification of Construction Works under the Air
Pollution Control (Construction Dust) Regulation |
||||
|
471691 |
14 Sep 2021 |
End of Project |
Notified |
- |
|
Chemical Waste Producer Registration |
||||
|
WPN5213-225-B2526-01 |
14 Mar 2018 |
End of Project |
Valid |
- |
|
Billing Account for Disposal of Construction Waste |
||||
|
7029997 |
1 Feb 2018 |
End of Project |
Valid |
- |
|
GW-RE0338-26 |
10
Apr 26 |
9 Oct 26 |
Valid |
Construction
Noise Permit for Welding at Column E, G & H |
|
GW-RE0425-26 |
22
Apr 26 |
16 Oct 26 |
Valid |
Construction
of Noise Enclosure at Zone 2 & 3 West Side |
|
GW-RE0532-26 |
21
May 26 |
20 Nov 26 |
Valid |
Welding
Works at Column C & D |
|
GW-RE0646-26 |
13
Jun 26 |
12 Nov 26 |
Valid |
Construction
of Noise Enclosure at Zone 2 East Side |
|
GW-RE0684-26 |
1
Jul 26 |
30 Sep 26 |
Valid till 30 Sep 26 |
Construction
Noise Permit for Erection of Noise Enclosure at Ferry Street Southbound |
|
GW-RE0880-26 |
1
Aug 26 |
30 Sep 26 |
Valid till 30 Sep 26 |
Night
works for TTA Implementation at Ferry Street, Yan Cheung Road and Kansu
Street |
|
GW-RE0901-26 |
1
Sep 26 |
30 Nov 26 |
Valid |
Night
works for Erection of Noise Enclosure at Canton Road and Kansu Street |
|
GW-RE0912-26 |
1
Sep 26 |
30 Nov 26 |
Valid |
Night
works for Construction of New GRF at Temple Street |
|
GW-RE0913-26 |
1
Sep 26 |
30 Nov 26 |
Valid |
Night
works for Construction of New GRF at Shanghai Street |
|
GW-RE0909-26 |
1
Sep 26 |
30 Nov 26 |
Valid |
Night
works for Construction of New GRF at Battery Street |
|
GW-RE0900-26 |
1
Sep 26 |
30 Nov 26 |
Valid |
Erection
of Noise Enclosure at Public Square Street |
|
GW-RE0933-26 |
1
Sep 26 |
30 Nov 26 |
Valid |
Erection
of Enclosure at Zone 1-3 |
|
Marine
Dumping Permit |
||||
|
Nil |
- |
- |
- |
- |
Environmental
permit (EP) conditions under the EIAO, submission status under the EP and
implementation status of mitigation measures had been reviewed and implemented on schedule. The status of
required submissions under the EP (EP-457/2013/D) and FEP (FEP-03/457/2013/D)
as of the reporting period for the Project are summarised in Table 2.1
Table 2.1 Summary of
Status of Required Submission for EP-457/2013/D and
FEP-03/457/2013/D
for the Project
|
EP/FEP Condition (EP-457/2013/D) (FEP-03/457/2013/D) |
Submission |
Submission date |
|
10 September 2026 |
Details of the
major construction activities reported by Main Contractor in this reporting
period are shown in Table 2.2.
Table
2.2 Summary of the Construction Activities reported by Main Contractor during
the Reporting Month
|
Construction
activities undertaken |
Remarks on
progress |
|
l Remaining drainage, utilities and reinstatement
works at Ferry Street and Yan Cheung Road. |
l 90% completion |
|
l GRF Bridge Works – Continue rectification of defects
and other associated works |
l 98% completion |
|
l Works at Zone 1 Noise Enclosure – Continue
installation of PMMA panels and absorptive panels and cable brackets for
linear heat detection cables and laying of lighting cables. |
l 93% completion |
|
l Works at Zone 3 Noise Enclosure – F02 - Continue
installation of cable brackets for linear heat detection cables, lighting
cables, cable containments and light fittings, brackets, trunking and copper
pipe. C07 Noise Enclosure – Continue installation of steel tie beams and main
beams. |
l 93% completion |
|
l Works at Zone 2 Noise Enclosure – Continue
installation of main beams, secondary tie beams, smoke ventilators,
absorptive panels and PMMA panels. |
l 84% completion |
The drawing
showing the project layout and the location of the monitoring station and
environmental sensitive receivers are attached in Appendix A and Appendix K.
Co-ordinates of the monitoring location are shown in Table 2.3.
Table 2.3 Summary for the location of the monitoring
station
|
Monitoring Location |
Location ID |
Latitude |
Longitude |
|
Yau Ma Tei Catholic Primary School (Hoi Wang Road)* |
W-A1/ W-N1A |
22.31345 |
114.16409 |
|
Man Cheong Building |
W-A6 |
||
|
Hydan Place |
W-N18 |
||
|
Prosperous Garden Block 1 |
W-N25A |
||
|
The Coronation Tower 1 |
W-P11 |
||
|
Remark: *The High Volume Sampler (HVS) at dust
impact monitoring location W-A1 had been relocated on 6 Sep 2022 due to
installation work of PV panel at Yau Ma Tei Catholic Primary School. The
relocation of HVS was approved by ER and agreed with IEC. |
|||
Air
Quality
The impact
monitoring had been carried out in accordance with section 5.8 of the approved
EM&A Manual to determine the 1-hour and 24-hour total suspended
particulates (TSP) levels at the monitoring locations in the reporting month.
The sampling
frequency of at least once in every 6 days, shall be strictly observed at the
monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the
sampling frequency of at least 3 times in every 6 days should be undertaken
when the highest dust impact occurs.
General
meteorological conditions (wind speed, direction and precipitation) and notes
regarding any significant adjacent dust producing sources had also been
recorded throughout the impact monitoring period.
Noise
Construction noise
level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30min) shall be used as the monitoring
parameter for the time period between 0700 and 1900 hours on normal weekdays.
For all other time
periods, Leq (5min) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
As supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
Air Quality
1-hour TSP levels
and 24-hour TSP had been measured with direct reading dust meter and High
Volume Samplers respectively. It has been demonstrated its capability in achieving
comparable results with high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50).
The 1-hour TSP
meter was calibrated by the manufacturer prior to purchasing. Zero response of
the instrument was checked before and after each monitoring event.
Operation of the 1-hour TSP meter followed manufacturer’s Operation and Service
Manual. The 24-hour TSP meter was calibrated against firmware 80570-8100-V1.0.4,
annually. Operation of the 24-hour TSP meter followed manufacturer’s Operation
and Service Manual. Valid calibration
certificates of dust monitoring equipment are attached in Appendix H.
A summary of the
equipment that was deployed for the 24- hour averaged monitoring is shown in
Table 3.1. The TSP monitoring was conducted as per the schedule presented in
Appendix G.
The equipment used
for 1-hour TSP and 24-hour TSP measurement and calibration are summarised in
Table 3.1
Table 3.1 Construction
Dust Monitoring Equipment
|
Monitoring
Parameter |
Monitoring
Equipment |
Serial
Number |
Date
of Calibration |
|
1-hour
TSP |
LD-5R Digital
Dust Indicator |
467358 |
26 August 2026 |
|
LD-5R Digital
Dust Indicator |
467360 |
26 August 2026 |
|
|
LD-5R Digital
Dust Indicator |
882107 |
26 August 2026 |
|
|
24-hour TSP |
TE-5170X High
Volume Sampler |
1084 |
21 August 2026,
05 September 2026 and 18 September 2026 |
|
TE-5170X High
Volume Sampler |
1050 |
21 August 2026,
05 September 2026 and 20 September 2026 |
|
|
TE-5028A
Calibration Kit |
3702 |
02 January 2026 |
|
|
TE-5025A
Calibration Kit |
3465 |
08 December 2025 |
Noise
Sound level meter
in compliance with the International Electrotechnical Commission Publications
651: 1979 (Type 1) and 804: 1985 (Type 1) specifications has been used for
carrying out the noise monitoring. The sound level meter has been checked using
an acoustic calibrator. The wind speed and other metrological data has been
recorded from Hong Kong Observatory- King’s Park meteorological station, along
with portable wind speed meter stand by as back up when the information are not available from HKO.
Acoustic
calibrators and sound level meters using for the monitoring is within the valid
period and were calibrated per year. Valid calibration certificate of noise monitoring equipment is attached
in Appendix I.
The details of
equipment using for monitoring are listed in Table 3.2, as below:
Table 3.2 Monitoring
Equipment Used in Monitoring
|
Monitoring
Equipment |
Serial
Number |
Date
of Calibration |
|
NTi XL3 Sound Level Meter |
A3A-01229-F0 |
23 July 2026 |
|
Rion NC-75 Sound
Level Calibrator |
35124527 |
13 January 2026 |
|
Rion NC-75 Sound
Level Calibrator |
34524163 |
14 July 2026 |
Monitoring
Methodology and QA/QC results
Air
Quality
The 1-hour TSP
monitor, portable dust meters (Sibata Digital Dust Indicator Model LD-5R and
PC-3A(E) digital dust indicator) were used for the impact monitoring. The
1-hour TSP meters provides a real time 1-hour TSP measurement based on 90o
light scattering. Three 1-hour TSP level were logged per every six days.
The 24-hour TSP
monitor, High Volume Samplers (Tisch TE-5170X High Volume Air Sampler) were
used for the impact monitoring. The 24-hour TSP monitoring consists of the
following:
u The HVS
was set at the monitoring location, with electricity supply connected and
secured;
u HVS was
calibrated before commencing the 1st measurement;
u The filter
paper was weight and provided by HOKLAS lab (Acumen Laboratory and Testing
Limited and ALS Technichem (HK) Pty Ltd) before and after the sampling.
Certificate of HOKLAS accredited laboratory can be referred to Appendix J;
u The
airflow over time during sampling process was recorded by the HVS.
HVSs were free-standing with no obstruction. The following
criteria were considered in the installation of the HVS:
u Appropriate
support to secure the samples against gusty wind needed to be provided the monitoring
station;
u A
minimum of 2m separation from walls, parapets and penthouses was required for
rooftop samplers;
u No
furnace or incinerator flues was nearby;
u Airflow
around the sampler was unrestricted; and
u Permission
could be obtained to set up the samplers and gain access to the monitoring
station.
u Glass
fiber filters were labelled and sufficient filters that were clean and without
pinholes were selected;
u All filters
were equilibrated in the conditioning environment for 24 hours before weighing.
The conditioning environment temperature was around 25℃ and not varied by
more than ±3℃; the relative humidity (RH)was 40%; and
u Acumen
Laboratory and Testing Limited and ALS Technichem (HK) Pty Limited, as HOKLAS
accredited laboratory, implemented comprehensive quality assurance and quality
control programmes on the filters.
u The power
supply was checked to ensure that the HVS was working properly;
u The
filter holder and area surrounding the filter were cleaned;
u The
filter holder was removed by loosening the foul bolts and a new filter, with
stamped number upward, on a supporting screen was aligned carefully;
u The
filter was properly aligned on the screen so that the gasket formed an airtight
seal on the outer edges of the filter;
u The
swing bolts were fastened to hold the filter holder down to the frame. The pressure
applied should be sufficient to avoid air leakage at the edges;
u The
shelter lid was closed and secured with an aluminum strip;
u The HVS
was warmed- up for about 5 minutes to establish run- temperature conditions;
u A new
flow rate record sheet was inserted into the flow recorder;
u The
flow rates of the HVS was checked and adjusted to between 0.62-1.30m3min-1,
which was within the range specified in the EM&A Manual (i.e. 0.6- 1.7m3min-1);
u The programmable
timer was set for a sampling period of 24 hours, and the starting time, weather
condition and filter number were recorded;
u The
initial elapsed time was recorded;
u At the
end of sampling, the sampled filter was removed carefully and folded in half so
that only surfaces with collected particulate matter were in contact;
u The
filter paper was placed in a clean plastic envelope and sealed; all monitoring
information was recorded on a standard data sheet and
u The filters
were sent to (Acumen Laboratory and Testing Ltd and ALS Technichem (HK) Pty
Ltd) for analysis.
u The HVS
and their accessories were maintained in a good working condition. For example,
motor brushes were replaced routinely and electrical wiring was checked to
ensure a continuous power supply; and
u The
flow rate of each HVS with mass flow controller was calibrated using an orifice
calibrator, Initial calibrations of the dust monitoring equipment were conducted
upon installation and prior to commissioning. Five- point calibration was
carried out for HVS using TE-5025A and TE-5028A Calibration Kit. HVS is
calibrated bimonthly. The calibration records for the HVS is given in Appendix
H.
u The
wind speed has been recorded from Hong Kong Observatory- King’s Park
meteorological station, along with portable wind speed meter stand by as back
up when the information are not available from HKO.
Noise
All noise
measurements by the meter were set to FAST response and on the A-weighted
equivalent continuous sound pressure level (Leq) in decibels dB(A).
LAeq(30min) was used as the monitoring metric for the time period
between 0700 –1900 hours on normal weekdays. The measured noise levels were
logged every 5 minutes throughout the monitoring period.
Prior to the noise
measurement, the accuracy of the sound level meter was checked using an
acoustic calibrator generating a known sound pressure level at a known frequency.
Checking was conducted before and after the monitoring. The calibration level
before and after the noise measurement is agreed to within 1.0 dB(A).
Noise measurements
should not be made in presence of fog, rain, wind with a steady speed exceeding
5 ms-1 or wind with gusts exceeding 10 ms-1. The wind
speed was checked with a portable wind speed meter capable of measuring with
speeds in ms-1.
Air Quality
During the site
visit, both of the original proposed dust monitoring locations were rejected
due to the condition at The Coronation was not favourable for monitoring and
the access was declined by the management office of Hong Kong Community College
(HKCC) of PolyU. Two alternative air monitoring stations Yau Ma Tei Catholic
Primary School (Hoi Wang Road) and Man Cheong Building had been proposed by ET
and approved by IEC. 2 designated air monitoring locations were identified and
agreed with IEC and EPD. Details of air monitoring stations are described in
Table 3.3. The location plan of air quality monitoring stations is shown in
Appendix K.
Table 3.3 Location
of the Dust Monitoring Stations
|
Air
Quality Monitoring Station |
Dust Monitoring |
|
W-A1 |
Yau Ma Tei Catholic Primary School (Hoi Wang Road) |
|
W-A6 |
Man Cheong Building |
Noise
During the site visit, one of the original proposed
noise monitoring locations Tak Cheong Building was rejected by the president of
the owner’s corporation. Alternative noise monitoring station Hydan place had
been proposed by ET and approved by IEC. 4 noise sensitive receivers designated
noise monitoring locations were identified and agreed with IEC and EPD. The
designated monitoring stations are identified and access was granted by the
premises. The details of noise monitoring stations are described in Table 3.4
and the location plan of noise monitoring station is shown in Appendix K.
Table 3.4 Noise
Monitoring Stations
|
Noise
Monitoring
Station |
Identified Noise Monitoring Station |
Type of Measurement |
|
W-N1A |
Yau Ma Tei Catholic Primary School (Hoi Wang Road) |
Façade |
|
W-N18 |
Hydan Place |
Façade |
|
W-N25A |
Prosperous Garden Block 1 |
Façade |
|
W-P11 |
The Coronation Tower 1 |
Façade |
Monitoring date,
time, frequency and duration
A summary of
impact monitoring duration, sampling parameter and frequency is presented in
Table 3.5.
Table 3.5 Summary of Impact Monitoring Programme
|
Impact Monitoring |
Duration |
Sampling Parameter |
Frequency |
|
Dust |
1-hour continuous measurement |
1-hour TSP |
3 times per six days |
|
Dust |
24-hour continuous sampling |
24-hour TSP |
Once per six days |
|
Noise |
30-minute continuous measurement |
Leq
30
min, L10 and L90
as reference. |
Once per
week (0700 – 1900) |
Air
Quality
According to our
field observations, the major dust source identified at the designated air
quality monitoring stations in the reporting month are summarised in Table 3.6.
Table 3.6
Observation at Dust Monitoring Stations
|
Monitoring Station |
Major Dust Source |
|
W-A1 |
Nearby traffic |
|
W-A6 |
Nearby traffic |
Air quality impact monitoring for the reporting month
was carried out on 03, 09, 15, 21, 25 and 29 September 2026.
The results for
1-hour TSP and 24-hour TSP are summarized in Table 3.7 and Table 3.8. The
measurement data and details of influencing factors such as weather conditions
and site observation are presented in Appendix L.
Table
3.7 Summary of 1-hour TSP Monitoring Results
|
Monitoring
Location |
Range(μg/m3) |
Action
Level(μg/m3) |
Limit
Level(μg/m3) |
|
W-A1 |
5
– 28 |
319 |
500 |
|
W-A6 |
7
– 21 |
306 |
500 |
Table
3.8 Summary of 24-hour TSP Monitoring Results
|
Monitoring
Location |
Range(μg/m3) |
Action
Level(μg/m3) |
Limit
Level(μg/m3) |
|
W-A1 |
36
– 45 |
167 |
260 |
|
W-A6 |
28
– 104 |
166 |
260 |
Noise
According to our
field observations, the major noise source identified at the designated noise
monitoring station in the reporting month are summarised in Table 3.9:
Table
3.9 Observation at Noise Monitoring Stations
|
Monitoring Station |
Major Noise Source |
|
W-N1A |
Nearby traffic |
|
W-N18 |
Nearby traffic |
|
W-N25A |
Nearby traffic |
|
W-P11 |
Nearby traffic |
The construction
noise impact monitoring for the
reporting month was carried out on 03, 09,
15, 21, 25 and 29 September 2026.
The result for noise monitoring is summarized in Table
3.10. The measurement data are shown in Appendix M.
Table 3.10
Summary of Noise Monitoring Results
|
Time
Period |
Monitoring location |
Parameter |
Range,
dB(A) |
|
|
||
|
Leq |
L10 |
L90 |
Action
Level |
Limit
Level# |
|||
|
Normal working
hour from 0700-1900 |
W-N1A* |
Leq
30min |
56.0 –
62.4 |
57.0 –
63.6 |
55.1 –
61.6 |
When
one documented complaint is received |
70dB(A)
or 65 dB(A) during examination |
|
W-N18 |
61.3 –
65.5 |
64.1 –
68.0 |
59.2 –
63.1 |
75dB(A)# |
|||
|
W-N25A |
62.8 –
66.6 |
67.8 –
75.9 |
60.8 –
64.9 |
||||
|
W-P11 |
64.2 –
66.4 |
65.7 –
68.9 |
63.1 –
64.9 |
||||
|
1. #
If works are to be carried out during restricted hours, the conditions
stipulated in the construction noise permit by the Noise Control Authority
have to be followed. 2.
* No examinations were scheduled
at Yau Ma Tei Catholic Primary School during the reporting month. The limit
level was 70 dB(A) in the reporting month. |
The waste generated from this Project includes inert
C&D materials, and non-inert C&D materials. Non-inert C&D materials
are made up of general refuse, vegetative wastes and recyclable wastes such as
plastics and paper/cardboard packaging waste. Steel materials generated from
the project are also grouped into non-inert C&D materials as the materials
were not disposed of with other inert C&D materials. With reference to
relevant handling records and trip tickets of this Project, the quantities of
different types of waste generated in the reporting month are summarised in
Table 3.11. Details of cumulative waste management data are
presented as a waste flow table in Appendix N.
Table
3.11 Quantities of waste generated from the Project
|
Reporting
period |
Quantity |
|||||
|
Inert
C&D Materials (in
‘tonnes) |
Chemical
Waste (in‘000
Kg) |
Non-inert
C&D Materials |
||||
|
Others, e.g.
General Refuse disposed at Landfill (in
‘tonnes) |
Recycled
materials |
|||||
|
Paper/card
board (in
‘000 Kg) |
Plastics (in
‘000 Kg) |
Metals (in
‘000 Kg ) |
||||
|
September 2026 |
582.50 |
0.00 |
24.70 |
0.00 |
0.00 |
0.00 |
Summary of Complaints, Notification of Summons and Prosecutions
The Environmental
Complaint Handling Procedure is shown in below Table 4.1:
Table
4.1 Environmental Complaint Handling Procedure
|
Complaint
Received via Project Hotline |
Complaint
Received via 1823 or from other government departments |
|||||
|
|
|
|
|
|||
|
Contractor
notify ER, ET and IEC |
ER
notify Contractor, ET and IEC |
|||||
|
|
|
|
|
|||
|
Contractor
log complaint and date of receipt onto the complaint database. Contractor,
ER and ET to conduct investigation of complaint |
||||||
|
|
|
|
|
|||
|
If
complaint is considered not valid |
If
complaint is found valid |
|||||
|
|
|
|
|
|||
|
ET or
ER to reply the complainant if necessary |
Contractor
to identify and implement remedial measures in consultation with the IEC, ET
and ER. |
|||||
|
|
|
|
|
|||
|
|
|
The ER, ET and IEC to review the effectiveness of the
Contractor's remedial measures and the updated situation; ET
to undertake additional monitoring and audit to
verify the situation if necessary, and oversee that circumstances leading to
the complaint do not recur. ER to conduct further inspection as
necessary. |
||||
|
|
|
|
|
|||
|
If
the complaint is referred by the EPD, the Contractor to prepare interim
report on the status of the complaint investigation and follow-up actions
stipulated above, including the details of the remedial measures and
additional monitoring identified or already taken, for submission to EPD
within the time frame assigned by the EPD |
||||||
|
|
|
|
||||
|
The
ET to record the details of the complaint, results of the investigation,
subsequent actions taken to address the complaint and updated situation
including the effectiveness of the remedial measures, supported by regular
and additional monitoring results in the monthly EM&A reports |
||||||
Should
non-compliance of the criteria occur, action in accordance with the Event and Action
Plan in Appendix D and Appendix E shall be carried out.
One
Action Level of construction noise was triggered during the reporting month as
one documented complaint regarding noise was received. No exceedance of Limit
Level of construction noise was recorded in the reporting month. No exceedance
of the Action and Limit Level of 24-hour TSP and 1-hour TSP was recorded in the
reporting month.
One environmental
complaint was received in the reporting month. After investigation with Contractor,
precautionary measures had been proposed to the Contractor by ET. The interim
reports for the complaints are shown in Appendix Q.
No non-compliance was reported in the reporting month.
No notification of
summon and prosecution was received in the reporting period.
Statistics on
complaints, notifications of summons and successful prosecutions are summarized
in Appendix O.
Site inspections were carried out on a weekly basis to
monitor the implementation of proper environmental pollution control and
mitigation measures under the Contract. In the reporting period, four (4) site inspections
were carried out on 03, 10, 17 and 24 September
2026, along with bi-weekly inspection of the implementation of landscape and
visual mitigation measures conducted on 10 and 24 September 2026.
One joint site inspection with IEC also undertaken on 10 September 2026. Minor deficiencies were observed
during weekly site inspection. Key observations during the site inspections are
summarized in Table 5.1.
Table 5.1 Site
Observations
|
Date |
Environmental
Observations |
Follow-up
Status |
|
03
September 2026 |
1.
Under
Ferry Street Flyover, NRMM label should be displayed on PME. |
1.
NRMM label was properly displayed on PME under Ferry
Street Flyover. |
|
10
September 2026 |
1.
On
Ching Ping Street and at Old Yau Ma Tei Carpark Building Area, NRMM labels
should be displayed conspicuously on PMEs on site. |
1.
NRMM
label was properly displayed on the excavator. The cherry picker at Yau Ma
Tei Old Carpark building area was transported away from site on that day. |
|
17
September 2026 |
1.
On
Ferry Street, it is reminded that stockpiles on site are to be properly
covered after work if they are not backfilled before the end of the day. |
1.
The stockpiles at Ferry Street were backfilled on
that day. |
|
24
September 2026 |
1.
Under
Ferry Street Flyover, the area with powered breaking works should be sprayed with
water often. |
1.
Continuous water spraying was carried out during the
breaking works under Ferry Street Flyover. |
The Contractor had rectified all observation
identified during environmental site inspection in the reporting period.
According to the EIA Study Report, Environmental
Permit, contract documents and EM&A Manual, the mitigation measures
detailed in the documents are implemented as much as practical during the
reporting period. An updated Implementation Status of Environmental Mitigation
Measures (EMIS) is provided in Appendix F.
Future Key Issues
The construction
activities provided by Main Contractor in the next reporting month are:
|
l Continuing
works on remaining drainage, utilities and reinstatement works at Ferry
Street and Yan Cheung Road l GRF
Bridge Works – Continue rectification of defects and other associated works l Works
at Zone 3 Noise Enclosure –Continue E&M works at F02. For C07 Noise Enclosure
– Continue installation of steel tie beams, absorptive panels, PMMA panels
and flashing. l Works
at Zone 2 Noise Enclosure – Continue installation of absorptive panels,
infill PMMA, flashings (Smoke vent system) and E&M works. l Works
at Zone 1 Noise Enclosure –Continue flashing works and E&M works and
continue steel works for NE (V08). l Noise
Enclosure steelworks fabrication at the yard in Zhuhai, China. l Monitoring
of settlement instrumentation for areas at YMT Police Station and Prosperous
Garden |
Potential
environmental impacts arising from the above construction activities are mainly
associated with dust, construction noise and waste management.
The construction programme for the Project for the
next reporting month is presented in Appendix B.
Conclusion and Recommendations
This 102nd
monthly EM&A Report presents the EM&A works undertaken during the
period from 01 September 2026 to 30 September 2026
in accordance with the EM&A Manual and the requirement under EP- 457/2013/D
and FEP-03/457/2013/D.
One Action
Level of construction noise was triggered during the reporting month as one
documented complaint regarding noise was received. No exceedance of Limit Level
of construction noise was recorded in the reporting month. No exceedance of the
Action and Limit Level of 24-hour TSP and 1-hour TSP was recorded in the
reporting month.
One environmental
complaint was received in the reporting month. After investigation with
Contractor, precautionary measures had been proposed to the Contractor by ET.
The interim reports for the complaints are shown in Appendix Q.
No non-compliance was reported in the reporting month.
No notification of
summons or prosecution was received in the reporting month.
Appendix A
Alignment and
Works Area For the Contract No. HY/2014/08

Appendix B
Construction
Programme

Appendix C
Project
Organization Chart
Project
O-Chart

Appendix D
Dust
Event-Action Plan (EAP)
EVENT |
ACTION |
|||
|
ET |
IEC |
ER |
CONTRACTOR |
|
|
ACTION LEVEL |
||||
|
1.Exceedance for one sample |
1. Identify source, investigate the causes of
exceedance and propose remedial measures; 2. Inform IEC and ER; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method. |
1. Notify Contractor. |
1. Rectify any unacceptable practice; 2. Amend working methods if appropriate. |
|
2.Exceedance for two or more consecutive samples |
1. Identify source; 2. Inform IEC and ER; 3. Advise the ER on the effectiveness of the
proposed remedial measures; 4. Repeat measurements to confirm findings; 5. Increase monitoring frequency to daily; 6. Discuss with IEC and Contractor on remedial
actions required; 7. If exceedance continues, arrange meeting with IEC
and ER; 8. If exceedance stops, cease additional monitoring. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible
remedial measures; 4. Advise the ET on the effectiveness of the
proposed remedial measures; 5. Supervise Implementation of remedial measures. |
1. Confirm receipt of notification of failure in
writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. |
1. Submit proposals for remedial to ER within 3
working days of notification; 2. Implement the agreed proposals; 3. Amend proposal if appropriate. |
|
LIMIT LEVEL |
||||
|
1.Exceedance for one sample |
1. Identify source, investigate the causes of
exceedance and propose remedial measures; 2. Inform ER, Contractor and EPD; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily; 5. Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible
remedial measures; 4. Advise the ER on the effectiveness of the
proposed remedial measures; 5. Supervise implementation of remedial measures. |
1. Confirm receipt of notification of failure in
writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. |
1. Take immediate action to avoid further
exceedance; 2. Submit proposals for remedial actions to IEC
within 3 working days of notification; Implement the agreed proposals; 4. Amend proposal if appropriate. |
|
2.Exceedance for two or more consecutive samples |
1. Notify IEC, ER, Contractor and EPD; 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency to daily; 5. Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 6. Arrange meeting with IEC and ER to discuss the
remedial actions to be taken; 7. Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 2. Review Contractor’s remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; 3. Supervise the implementation of remedial
measures. |
1. Confirm receipt of notification of failure in
writing; 2. Notify Contractor; 3. In consultation with the IEC, agree with the
Contractor on the remedial measures to be implemented; 4. Ensure remedial measures properly implemented; 5. If exceedance continues, consider what portion of
the work is responsible and instruct the Contractor to stop that portion of
work until the exceedance is abated. |
1. Take immediate action to avoid further
exceedance; 2. Submit proposals for remedial actions to IEC
within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not under
control; 5. Stop the relevant portion of works as determined
by the ER until the exceedance is abated. |
Note:
ET – Environmental
Team
ER – Engineer’s Representative
IEC – Independent Environmental Checker
Appendix E
Noise
Event-Action Plan (EAP)
EVENT |
ACTION |
|||
|
ET |
IEC |
ER |
CONTRACTOR |
|
|
Action Level |
1. Identify source, investigate the causes of
exceedance and propose remedial measures; 2. Notify IEC and Contractor; 3. Report the results of investigation to the IEC,
ER and Contractor; 4. Discuss with the Contractor and formulate
remedial measures; 5. Increase monitoring frequency to check mitigation
effectiveness. |
1.Review the analysed results submitted by the ET; 2. Review the proposed remedial measures by the
Contractor and advise the ER accordingly; 3. Supervise the implementation of remedial
measures. |
1. Confirm receipt of notification of failure in
writing; 2. Notify Contractor; 3. Require Contractor to propose remedial measures
for the analysed noise problem; 4. Ensure remedial measures are properly implemented |
1. Submit noise mitigation proposals to IEC; 2. Implement noise mitigation proposals. |
|
Limit Level |
1. Identify source; 2. Inform IEC, ER, EPD and Contractor; 3. Repeat measurements to confirm findings; 4. Increase monitoring frequency; 5. Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 6. Inform IEC, ER and EPD the causes and actions
taken for the exceedances; 7. Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 2. Review Contractors remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; 3. Supervise the implementation of remedial
measures. |
1.Confirm receipt of notification of failure in
writing; 2. Notify Contractor; 3. Require Contractor to propose remedial measures
for the analysed noise problem; 4. Ensure remedial measures properly implemented; 5. If exceedance continues, consider what portion of
the work is responsible and instruct the Contractor to stop that portion of
work until the exceedance is abated. |
1. Take immediate action to avoid further
exceedance; 2. Submit proposals for remedial actions to
IEC within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not under
control; 5. Stop the relevant portion of works as determined
by the ER until the exceedance is abated. |
Note:
ET – Environmental Team
IEC – Independent Environmental Checker
ER – Engineer’s Representative
Appendix F
Environmental Mitigation Implementation Schedule
(EMIS)
Environmental Mitigation Implementation
Schedule – Contract No. HY/2014/08 (Yau Ma Tei East) |
|
||||||||
|
|
|||||||||
|
EIA Ref. |
EM&A Log Ref. |
Recommended Mitigation
Measures |
Objectives of the
Recommended Measures & Main Concerns to address |
Implementation Agent |
Location / Timing |
Implementation Stage |
Requirements and/ or
standards to be achieved |
Implementation Status |
|
|
Construction Dust Impact |
|||||||||
|
S4.3.10 |
D1 |
The contractor shall follow the procedures and requirements
given in the Air Pollution Control (Construction Dust) Regulation |
Minimize dust impact at the nearby sensitive receivers |
Contractor |
All construction sites |
Construction stage |
· APCO · To control the dust impact To meet HKAQO and TM-EIA criteria |
· Implemented |
|
|
S4.3.10 |
D2 |
· Mitigation measures in form of regular watering under a good
site practice should be adopted. Watering once per hour on exposed
worksites and haul road should be conducted to achieve dust removal
efficiencies of 91.7%. While the above watering frequencies are to be
followed, the extent of watering may vary depending on actual site conditions
but should be sufficient to maintain an equivalent intensity of no less than
1.3 L/m2 to achieve the dust removal efficiency. |
Minimize dust impact at the nearby sensitive receivers |
Contractor |
All construction sites |
Construction stage |
· APCO · To control the dust impact To meet HKAQO and TM-EIA criteria |
· Implemented |
|
|
S4.3.10 |
D3 |
·
Proper watering at exposed soil should be undertaken throughout
the construction phase; ·
Any excavated or stockpile of dusty material should be covered entirely
by impervious sheeting or sprayed with water to maintain the entire surface
wet and then removed or backfilled or reinstated where practicable within 24
hours of the excavation or unloading; ·
Any dusty materials remaining after a stockpile is removed
should be wetted with water and cleared from the surface of roads; ·
A stockpile of dusty material should not be extended beyond the
pedestrian barriers, fencing or traffic cones; · The load of dusty materials on a vehicle leaving a construction
site should be covered entirely by impervious sheeting to ensure that the
dusty materials do not leak from the vehicle. · Where practicable, vehicle washing facilities with high pressure
water jet should be provided at every discernible or designated vehicle exit
point. The area where vehicle washing takes place and the road section
between the washing facilities and the exit point should be paved with concrete,
bituminous materials or hardcores; · When there are open excavation and reinstatement works, hoarding
of not less than 2.4m high should be provided and properly maintained as far
as practicable along the site boundary with provision for public
crossing. Good site practice shall also be adopted by the Contractor to
ensure the conditions of the hoardings are properly maintained throughout the
construction period; · The portion of any road leading only to construction site that is
within 30m of a vehicle entrance or exit should be kept clear of dusty
materials; · Surfaces where any pneumatic or power-driven drilling, cutting,
polishing or other mechanical breaking operation takes place should be
sprayed with water or a dust suppression chemical continuously; · Any area that involves demolition activities should be sprayed
with water or a dust suppression chemical immediately prior to, during and
immediately after the activities so as to maintain the entire surface wet; ·
Any skip hoist for material transport should be totally enclosed
by impervious sheeting; ·
Every stock of more than 20 bags of cement or dry-pulverised
fuel ash (PFA) should be covered entirely by impervious sheeting or placed in
an area sheltered on the top and the 3 sides; ·
Loading, unloading, transfer, handling or storage of bulk cement
or dry PFA should be carried out in a totally enclosed system or facility,
and any vent or exhaust should be fitted with an effective fabric filter or equivalent
air pollution control system ·
Exposed earth should be properly treated by compaction, turfing,
hydroseeding, vegetation planting or sealing with latex, vinyl, bitumen,
shotcrete or other suitable surface stabilizer within six months after the
last construction activity on the construction site or part of the
construction site where the exposed earth lies. |
Minimize dust impact at the nearby sensitive receivers |
Contractor |
All construction sites |
Construction stage |
· APCO · To control the dust impact To meet HKAQO and TM-EIA criteria |
· Implemented after reminder |
|
|
S4.3.10 |
D6 |
Implement regular dust monitoring under EM&A programme
during the construction stage. |
Monitoring of dust impact |
Contractor |
Selected rep. dust monitoring station |
Construction stage |
· TM-EIA |
· Implemented |
|
|
Construction
Noise (Airborne) |
|||||||||
|
S5.4.1 |
N1 |
Implement the following good site practices: · Only well-maintained plant should be operated on-site and plant should
be serviced regularly during the construction programme; · Machines and plant (such as trucks, cranes) that may be in
intermittent use should be shut down between work periods or should be
throttled down to a minimum; · Plant known to emit noise strongly in one direction, where
possible, be orientated so that the noise is directed away from nearby NSRs; · Silencers or mufflers on construction equipment should be
properly fitted and maintained during the construction works; · Mobile plant should be sited as far away from NSRs as possible
and practicable; · Material stockpiles, mobile container site office and other
structures should be effectively utilized, where practicable, to screen noise
from on-site construction activities. |
Control construction airborne noise |
Contractor |
All construction sites |
Construction stage |
· Annex 5, TM-EIAO |
· Implemented |
|
|
S5.4.1 |
N2 |
Install temporary hoarding located on the site boundaries between
noisy construction activities and NSRs. The conditions of hoardings
shall be properly maintained throughout the construction period. |
Reduce the construction noise levels at low-level zone of NSRs
through partial screening |
Contractor |
All construction sites |
Construction stage |
· Annex 5, TM-EIAO |
· Implemented |
|
|
S5.4.1 |
N3 |
Install movable noise barriers (typical design is wooden framed
barrier with a small-cantilevered on a skid footing with 25mm thick internal sound
absorptive lining), acoustic mat or full enclosure, screen the noisy plants
including air compressors, generators and handheld breakers, etc. |
Sreen the noisy plant items to be used at all construction sites |
Contractor |
All construction sites where practicable |
Construction stage |
· Annex 5, TM-EIAO |
· Implemented |
|
|
S5.4.1 |
N4 |
Use ‘Quiet plant’ |
Reduce the noise levels of plant items |
Contractor |
All construction sites where practicable |
Construction stage |
· Annex 5, TM-EIAO |
· Implemented |
|
|
S5.4.1 |
N5 |
Loading/ unloading activities should be carried out inside the
full enclosure of mucking out points. |
Reduce the noise levels of loading/ unloading activities |
Contractor |
Mucking out locations |
Construction stage |
· Annex 5, TM-EIAO |
· Implemented |
|
|
S5.4.1 |
N6 |
Sequencing operation of construction plants where practicable. |
Operate sequentially within the same work site to reduce the
construction airborne noise |
Contractor |
All construction sites where practicable |
Construction stage |
· Annex 5, TM-EIAO |
· Implemented |
|
|
S5.4.1 |
N7 |
Implement a noise monitoring programme under EM&A programme.
|
Monitor the construction noise levels at the selected
representative locations |
Contractor |
Selected rep. noise monitoring station |
Construction stage |
· TM-EIAO |
· Implemented |
|
|
Water Quality
(Construction Phase) |
|||||||||
|
S6.9.1.1 |
W1 |
In accordance with the Practice Note for Professional Persons on
Construction Site Drainage, Environmental Protection Department, 1994 (ProPECC
PN1/94), construction phase mitigation measures shall include the following: Construction Runoff · At the start of site establishment, perimeter cut-off drains to
direct off-site water around the site should be constructed with internal
drainage works and erosion and sedimentation control facilities
implemented. Channels (both temporary and permanent drainage pipes and
culverts), earth bunds or sand bag barriers should be provided on site to
direct stormwater to silt removal facilities. The design of the
temporary on-site drainage system will be undertaken by the contractor prior
to the commencement of construction; · The dikes or embankments for flood protection should be
implemented around the boundaries of earthwork areas. Temporary ditches
should be provided to facilitate the runoff discharge into an appropriate
watercourse, through a silt/ sediment trap. The sediment/ silt traps
should be incorporated in the permanent drainage channels to enhance
deposition rates; · The design of efficient silt removal facilities should be based
on the guidelines in Appendix A1 of ProPECC PN 1/94, which states that the
retention time for silt/ sand traps should be 5 minutes under maximum flow
conditions. Sizes may vary depending upon the flow rate, but for a flow
rate of 0.1 m3/s a sedimentation basin of 30 m3 would be required and for a
flow rate of 0.5 m3/s the basin would be 150 m3. The detailed design of
the sand/ silt traps shall be undertaken by the contractor prior to the
commencement of construction; · All exposed earth areas should be completed and vegetated as
soon as possible after earthworks have been completed, or alternatively,
within 14 days of the cessation of earthworks where practicable.
Exposed slope surfaces should be covered by tarpaulin or other means; · The overall slope of the site should be kept to a minimum to reduce
the erosive potential of surface water flows, and all traffic areas and
access roads protected by coarse stone ballast. An additional advantage
accruing from the use of crushed stone is the positive traction gained during
prolonged periods of inclement weather and the reduction of surface sheet
flows; · All drainage facilities and erosion and sediment control
structures should be regularly inspected and maintained to ensure proper and efficient
operation at all times and particularly following rainstorms. Deposited
silt and grit should be removed regularly and disposed of by spreading evenly
over stable, vegetated areas; · Measures should be taken to minimize the ingress of site
drainage into excavations. If the excavation of trenches in wet periods
is necessary, they should be dug and backfilled in short sections wherever
practicable. Water pumped out from trenches or foundation excavations
should be discharged into storm drains via silt removal facilities; · Open stockpiles of construction materials (for example,
aggregates, sand and fill material) of more than 50m3 should be covered with
tarpaulin or similar fabric during rainstorms. Measures should be taken
to prevent the washing away of construction materials, soil, silt or debris
into any drainage system; · Manholes should always be adequately covered and temporarily sealed
so as to prevent silt, construction materials or debris being washed into the
drainage system and storm runoff being directed into foul sewers; · Precautions be taken at any time of year when rainstorms are
likely, actions to be taken when a rainstorm is imminent or forecasted, and
actions to be taken during or after rainstorms are summarized in Appendix A2
of ProPECC PN 1/94. Particular attention should be paid to the control
of silty surface runoff during storm events, especially for areas located
near steep slopes; · All vehicles and plant should be cleaned before leaving a
construction site to ensure no earth, mud, debris and the like is deposited
by them on roads. An adequately designed and site wheel washing
facilities should be provided at every construction site exit where
practicable. Wash-water should have sand and silt settled out and
removed at least on a weekly basis to ensure the continued efficiency of the
process. The section of access road leading to, and exiting from, the
wheel wash bay to the public road should be paved with sufficient backfall
toward the wheel wash bay to prevent vehicle tracking of soil and silty water
to public roads and drains; · Oil interceptors should be provided in the drainage system
downstream of any oil/ fuel pollution sources. The oil interceptors
should be emptied and cleaned regularly to prevent the release of oil and
grease into the storm water drainage system after accidental spillage.
A bypass should be provided for the oil interceptors to prevent flushing
during heavy rain; · Construction solid waste, debris and rubbish on site should be
collected, handled and disposed of properly to avoid water quality impacts; · All fuel tanks and storage areas should be provided with locks and
sited on sealed areas, within bunds of a capacity equal to 110% of the
storage capacity of the largest tank to prevent spilled fuel oils from
reaching water sensitive receivers nearby; · Adopt best management practices; · All earth works should be conducted sequentially to limit the
amount of construction runoff generated from exposed areas during the wet
season (April to January) as far as practicable. |
To minimize water quality impact from the construction site runoff
and general construction activities |
Contractor |
All construction sites where practicable |
Construction stage |
· Water Pollution Control
Ordinance · ProPECC PN 1/94 · TM-EIAO · TM-DSS |
· Implemented |
|
|
S6.9.1.2 |
W2 |
Tunneling Works and Underground Works · Cut-&-cover tunneling work should be conducted sequentially
to limit the amount of construction runoff generated from exposed areas
during the wet season (April to January) as far as practicable. · Uncontaminated discharge should pass through sedimentation tanks
prior to off-site discharge; · The wastewater with a high concentration of SS should be treated
(e.g. by sedimentation tanks with sufficient retention time) before
discharge. Oil interceptors would also be required to remove the oil,
lubricants and grease from the wastewater; · Direct discharge of the bentonite slurry (as a result of D-wall)
is not allowed. It should be reconditioned and reused wherever
practicable. Temporary storage locations (typically a properly closed
warehouse) should be provided on site for any unused bentonite that needs to
be transported away after all the related construction activities area
completed. The requirements in ProPECC PN 1/94 should be adhered to in
the handling and disposal of bentonite slurries. |
To minimize construction water quality impact from tunneling
works |
Contractor |
All tunneling portion |
Construction stage |
· Water Pollution Control
Ordinance · ProPECC PN 1/94 · TM-DSS · TM-EIAO |
· Implemented |
|
|
S6.9.1.3 |
W3 |
Sewage Effluent · Portable chemical toilets and sewage holding tanks are
recommended for handling the construction sewage generated by the
workforce. A licensed contractor should be employed to provide
appropriate and adequate portable toilets and be responsible for appropriate
disposal and maintenance. |
To minimize water quality from sewage effluent |
Contractor |
All construction sites where practicable |
Construction stage |
· Water Pollution Control
Ordinance · TM-DSS |
· Implemented |
|
|
S6.9.1.5 |
W4 |
Groundwater from Potential Contaminated Area: · No direct discharge of groundwater from contaminated areas
should be adopted. · A discharge license under the WPCO through the Regional Office
of EPD for groundwater discharge should be applied. Prior to the excavation
works within these potentially contaminated areas, the groundwater quality
should be reviewed during the process of discharge license application. The
compliance to the Technical Memorandum on Standards for Effluents Discharged
into Drainage on Sewerage Systems, Inland and Coastal Waters (TM-DSS) and the
existence of prohibited substance should be confirmed. If the review results
indicated that the groundwater to be generated from the excavation works
would be contaminated, the contaminated groundwater should be either properly
treated in compliance with the requirements of the TM-DSS or properly
recharged into the ground. · If wastewater treatment is deployed, the wastewater treatment
unit shall deploy suitable treatment process (e.g. oil interceptor /
activated carbon) to reduce the pollution level to an acceptable standard and
remove any prohibited substances (e.g. TPH) to undetectable range. All
treated effluent from wastewater treatment plant shall meet the requirements
as stated in TM-DSS and should be discharged into the foul sewers. · If groundwater recharging wells are deployed, recharging wells should
be installed as appropriate for recharging the contaminated groundwater back
into the ground. The recharging wells should be selected at places where the
groundwater quality will not be affected by the recharge operation as
indicated in the Section 2.3 of TM-DSS. The baseline groundwater quality
shall be determined prior to the selection of the recharge wells, and submit
a working plan (including the laboratory analytical results showing the
quality of groundwater at the proposed recharge location(s) as well as the
pollutant levels of groundwater to be recharged) to EPD for agreement.
Pollution levels of groundwater to be recharged shall not be higher than
pollutant levels of ambient groundwater at the recharge well. Prior to
recharge, any prohibited substances such as TPH products should be removed as
necessary by installing the petrol interceptor. |
To minimize groundwater quality impact from contaminated area |
Contractor |
Excavation areas where contamination is found |
Construction stage |
· Water Pollution Control
Ordinance · TM-DSS · TM-EIAO |
· Implemented |
|
|
S6.9.1.6 |
W6 |
Accidental Spillage In order to prevent accidental spillage of chemicals, the
following is recommended: ·
All the tanks, containers, storage area should be bunded and the
locations should be locked as far as possible from the sensitive watercourse
and stormwater drains; ·
The Contractor should register as a chemical waste producer if
chemical wastes would be generated. Storage of chemical waste arising
from the construction activities should be stored with suitable labels and
warnings. Disposal of chemical wastes should be conducted in compliance
with the requirements as stated in the Waste Disposal (Chemical Waste)
(General) Regulation. |
To minimize water quality impact from accidental spillage |
Contractor |
All construction site where practicable |
Construction stage |
· Water Pollution Control
Ordinance · ProPECC PN 1/94 · TM-EIAO · TM-DSS |
· Implemented |
|
|
Waste Management (Construction Waste) |
|||||||||
|
S7.4.1 |
WM1 |
On-site sorting of C&D material · Geological assessment should be carried out by competent persons
on site during excavation to identify materials which are not suitable to use
as aggregate in structural concrete (e.g. volcanic rock, Aplite dyke rock,
etc.). Volcanic rock and Aplite dyke rock should be separated at the
source sites as far as practicable and stored at designated stockpile area
preventing them from delivering to crushing facilities. The crushing
plant operator should also be reminded to set up measures to prevent
unsuitable rock from ending up at concrete batching plants and be turned into
concrete for structural use. Details regarding control measures at
source site and crushing facilities should be submitted by the Contractor for
the Engineer to review and agree. In addition, site records should also
be kept for the types of rock materials excavated and the traceability of
delivery will be ensured with the implementation of Trip Ticket System and
enforced by site supervisory staff as stipulated under DEVB TC(W) No. 6/2010
for tracking of the correct delivery to the rock crushing facilities for
processing into aggregates. Alternative disposal option for the reuse
of volcanic rock and Aplite Dyke rock, etc. should be explored. |
Separation of unsuitable rock from ending up at concrete
batching plants and be turned into concrete for structural use |
Contractor |
All construction sites |
Construction stage |
· DEVB (W) No. 6/2010 |
· Implemented |
|
|
S7.5.1 |
WM2 |
Construction and Demolition Material · Maintain temporary stockpiles and reuse excavated fill material
for backfilling and reinstatement; · Carry out on-site sorting; · Make provisions in the Contract documents to allow and promote the
use of recycled aggregates where appropriate; · Adopt ‘selective demolition’ technique to demolish the existing
structures and facilities with a view to recovering broken concrete
effectively for recycling purpose, where possible; · Implement a trip-ticket system for each works contract to ensure
that the disposal of C&D materials are properly documented and verified;
and · Implement an enhanced Waste Management Plan similar to ETWBTC (Works)
No. 19/2005 – “Environmental Management on Construction Sites” to encourage
on-site sorting of C&D materials and to minimize their generation during
the course of construction. |
Good site practice to minimize the waste generation and recycle
the C&D materials as far as practicable so as to reduce the amount for
final disposal |
Contractor |
All construction sites |
Construction stage |
· Land (Miscellaneous Provisions)
Ordinance · Waste Disposal Ordinance · ETWB TCW No. 19/2005 |
· Implemented |
|
|
S7.5.1 |
WM3 |
C&D Waste · Standard formwork or pre-fabrication should be used as far as
practicable in order to minimize the arising of C&D materials. The
use of more durable formwork or plastic facing for the construction works
should be considered. Use of wooden hoardings should not be used, as in
other projects. Metal hoarding should be used to enhance the
possibility of recycling. The purchasing of construction materials will
be carefully planned in order to avoid over ordering and wastage; · The Contractor should recycle as much of the C&D materials
as possible on-site. Public fill and C&D waste should be segregated and
stored in different containers or skips to enhance reuse or recycling of
materials and their proper disposal. Where practicable, concrete and
masonry can be crushed and used as fill. Steel reinforcement bar can be
used by scrap steel mills. Different areas of the sites should be
considered for such segregation and storage. |
Good site practice to minimize the waste generation and recycle
the C&D materials as far as practicable so as to reduce the amount for
final disposal |
Contractor |
All construction sites |
Construction stage |
· Land (Miscellaneous Provisions)
Ordinance · Waste Disposal Ordinance · ETWB TCW No. 19/2005 |
· Implemented |
|
|
S7.5.1 |
WM5 |
Land-based Sediment · All construction plant and equipment shall be designed and
maintained to minimize the risk of silt, sediments, contaminants or other pollutants
being released into the water column or deposited in the locations other than
designated location; · All vessels shall be sized such that adequate draft is
maintained between vessels and the sea bed at all states of the tide to
ensure that undue turbidity is not generated by turbulence from vessel
movement or propeller wash; · Before moving the vessels which are used for transporting
dredged material, excess material shall be cleaned from the decks and exposed
fittings of vessels and the excess materials shall never be dumped into the
sea except at the approved locations; · Adequate freeboard shall be maintained on barges to ensure that
decks are not washed by wave action. · The Contractors shall monitor all vessels transporting material
to ensure that no dumping outside the approved location takes place. The
Contractor shall keep and produce logs and other records to demonstrate
compliance and that journeys are consistent with designated locations and copies
of such records shall be submitted to the engineers; · The Contractors shall comply with the conditions in the dumping
license. · All bottom dumping vessels (Hopper barges) shall be fitted with
tight fittings seals to their bottom openings to prevent leakage of material; · The material shall be placed into the disposal pit by bottom
dumping; · Contaminated marine mud shall be transported by spit barge of
not less than 750m3 capacity and capable of rapid opening and discharge at
the disposal site; · Discharge shall be undertaken rapidly and the hoppers shall be
closed immediately. Material adhering to the sides of the hopper shall not be
washed out of the hopper and the hopper shall remain closed until the barge
returns to the disposal site. · For Type 3 special disposal treatment, sealing of contaminant
with geosynthetic containment before dropping designated mud pit would be a
possible arrangement. A geosynthetic containment method is a method whereby
the sediments are sealed in geosynthetic containers and, the containers would
be dropped into the designated contaminated mud pit where they would be
covered by further mud disposal and later by the mud pit capping at the disposal
site, thereby fulfilling the requirements for fully confined mud disposal. |
To control pollution due to marine sediment |
Contractor |
Along CKR alignment |
Construction stage |
· ETWB TCW No. 34/2002 |
· Implemented |
|
|
S7.5.1 |
WM6 |
Chemical Waste · Chemical waste that is produced, as defined by Schedule 1 of the
Waste Disposal (Chemical Waste) (General) Regulation, should be handled in
accordance with the Code of Practice on the Packaging, Labelling and Storage
of Chemical Wastes; · Containers used for the storage of chemical wastes should be
suitable for the substance they are holding, resistant to corrosion,
maintained in a good condition, and securely closed, have a capacity of less than
450 L unless the specification has been approved by EPD, and display a label
in English and Chinese in accordance with instructions prescribed in Schedule
2 of the regulation; · The storage area for chemical wastes should be clearly labelled
and used solely for the storage of chemical waste, enclosed on at least 3
sides, have an impermeable floor and bunding of sufficient capacity to
accommodate 110% of the volume of the largest container or 20% of the total volume
of waste stored in that area, whichever is the greatest, have adequate
ventilation, covered to prevent rainfall entering, and arranged so that
incompatible materials are adequately separated; · Disposal of chemical waste should be via a licensed waste
collector, be to a facility licensed to receive chemical waste, such as the
Chemical Waste Treatment Centre which also offers a chemical waste collection
service and can supply the necessary storage containers, or be to a reuser of
the waste, under approval from EPD. |
Control the chemical waste and ensure proper storage, handling
and disposal |
Contractor |
All construction sites |
Construction stage |
· Waste Disposal (Chemical Waste)
(General) Regulation · Code of Practice on the
Packaging, Labelling and Storage of Chemical Waste |
· Implemented |
|
|
S7.5.1 |
WM7 |
General Refuse · General refuse generated on-site should be stored in enclosed
bins or compaction units separately from construction and chemical wastes; · A reputable waste collector should be employed by the Contractor
to remove general refuse from the site, separately from construction and
chemical wastes, on a daily basis to minimize odour, pest and litter
impacts. Burning of refuse on construction sites is prohibited by law. · Aluminum cans are often recovered from the waste stream by
individual collectors if they are segregated and made easily
accessible. Separate labelled bins for their deposit should be provided
if feasible; · Office wastes can be reduced through the recycling of paper if
volumes are large enough to warrant collection. Participation in a
local collection scheme should be considered by the Contractor. |
Minimize production of the general refuse and avoid odour, pest
and litter impacts |
Contractor |
All construction sites |
Construction stage |
· Waste Disposal Ordinance |
· Implemented |
|
|
Land
Contamination |
|
||||||||
|
S8.9 & Appendix 8.4 |
LC2 |
Excavation of the Contaminated Soil · Prior to commencement of the excavation works at the
contamination zone, the zone should be clearly marked out on site and the
surface levels recorded. Excavation of contaminated material should be
undertaken using dedicated earth-moving plant. · The excavated contaminated soils would be stockpiled at
designated area on site and covered by sheet to prevent dispersion of
contamination during stockpiling. · The Contractor should pay attention to the selection of suitable
groundwater lowering schemes and discharge points if the groundwater table is
higher than the contaminated soils during excavation. The Contractor should
also obtain a valid Water Pollution Control Ordinance (WPCO) discharge
licence from EPD where applicable. |
The contaminated soil will be excavated for on-site reuse |
Contractor |
PBH4 |
Prior to commencement of construction works within the
contaminated area |
· Practice Guide (PG) for
Investigation and Remediation of Contaminated Land · Guidance Notes for Contaminated
Land Assessment and Remediation · Guidance Manual for Use of
Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management |
· Implemented |
|
|
S8.9 & Appendix 8.4 |
LC3 |
· Following completion of the excavation to the specified depth,
at least one sample from the base of the excavation and four samples evenly
distributed along the boundary of the excavation shall be taken for a closure
assessment testing. The acceptance criterion is shown below:
· If the results of analysis below the RBRGs (Public Park), no
further excavation will be required. If the analysis indicates presence of contamination (i.e.
noncompliance of the acceptance criteria), further excavation shall be
carried out in 0.5m increment vertically and/or horizontally depending on the
location(s) of the sample(s) which has exceeded the acceptance criteria. Further
sampling shall also be conducted for compliance testing. The process of
excavation, sampling and compliance testing should continue until all
contaminated materials are removed and should be supervised by a Land
Contamination Specialist. |
· Implemented |
||||||
|
Appendix 8.4 |
LC4 |
A Remediation Report (RR) to demonstrate adequate clean-up shall
be prepared and submitted to EPD for endorsement prior to the commencement of
any construction/development works within the sites. No construction/development
works shall be carried out prior to the endorsement of the RR by EPD. |
· Implemented |
||||||
|
Hazard to Life |
|||||||||
|
S9.18 |
H1 |
Blasting activities regarding transport and use of explosives
should be supervised and audited by competent site staff to ensure full
compliance with the blasting permit conditions. |
To ensure that the risks from the proposed explosives handling
and transport would be acceptable |
Contractor |
Works areas at which explosives would be used |
Construction stage |
· Dangerous Goods Ordinance |
· N/A |
|
|
S9.6, para.4 |
H2 |
Detonators shall not be transported in the same vehicle with
other Category 1 Dangerous Goods. |
To reduce the risk of explosion during the transport of
cartridged emulsion |
Contractor |
- |
Construction stage |
· Dangerous Goods Ordinance |
· N/A |
|
|
S9.6, para.8 |
H3 |
The explosives delivery trucks should be approved by Mines
Division and should meet the regulatory requirements for transport of
explosives. |
To comply with the requirements for approval of an explosives
delivery vehicle |
Contractor |
- |
Construction stage |
· Dangerous Goods Ordinance |
· N/A |
|
|
S9.10, para.7 and S9.18 |
H4 |
Blast cover should be provided for shaft at HMT, and kept closed
during blasting. Provision of blast doors or heavy duty blast curtains should be
implemented at the shaft to prevent flyrock and control the air overpressure. |
To ensure safe use of explosives |
Contractor |
Shaft |
Construction stage |
- |
· N/A |
|
|
S9.16 |
H5 |
Only the required quantity of explosives for a particular blast
should be transported to avoid the return. |
To reduce risks during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H7 |
The approved truck dedicated for transport of explosives should
comply with the “Guidance Note on Requirements for Approval of an Explosives
Delivery Vehicle” issued by CEDD Mines Division. The truck should be periodically
inspected and properly maintained in good operation conditions. The
fuel carried in the fuel tank should be minimized to reduce the duration of
fire. Adequate fire fighting equipment shall be provided, inspected and
replaced periodically (e.g. fire extinguishers). |
To reduce the risk during explosives transport |
Contractor |
Works areas of which explosives would be used |
Construction stage |
· Dangerous Goods Ordinance |
· N/A |
|
|
S9.18 |
H8 |
The driver and his assistant should be physically healthy,
experienced and have good safe driving records. The driver should hold
a proper driving licence for the approved transport truck. Dedicated
training programme and regular road safety briefing sessions/ workshops
should be provided to enhance their safe driving attitude and practice.
Smoking should be strictly prohibited. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H9 |
Emergency response plans in case of road accident should be
prepared and implemented. The driver and his assistant should be
familiar with the emergency procedures including evacuation, and proper
communication/ fire-fighting equipment should be provided to the driver and
his assistant. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H10 |
Close liaison and communication among Mines Division,
Contractors for transport of explosives, and working staff of the blasting
should be established. In case of any change of work schedule leading
to cancellation or variation of explosives required, relevant parties should
be informed in time to avoid unused explosives at the work sites. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H11 |
Close liaison and communication with Fire Services Department
should be established to reduce the accidental detonation escalated from a
fire. The contractors for transport of explosives should use the
preferred transport routes as far as practicable. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H12 |
Contingency plan should be prepared for transport of explosives under
severe weather conditions such as rainstorms and thunderstorms. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H13 |
For explosive transport, all packages of explosives on the truck
should be properly stored in the truck compartment as required.
Packaging of the explosives should remain intact (i.e. damage free) until
they are transferred to the blasting site. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H14 |
Availability of a parking space should be ensured before
commencement of transport of explosives. Location for loading and
unloading of explosives should be as close as possible to the shaft. No
hot work should be performed in the vicinity during the time of loading and
unloading. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H22 |
It is recommended to explore to minimize the use of the
cartridged emulsion explosives and maximize the use of bulk emulsion
explosive as far as practicable. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
S9.18 |
H24 |
It is recommended to explore to use smaller explosive charges such
as ‘cast boosters’ or ‘mini-cast booster’ instead of cartridged emulsion as
primers for bulk emulsion. This option reduces the quantity of
explosives required for transportation for the sections where bulk emulsion
will be used. |
To reduce the risk during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
· N/A |
|
|
Landscape
& Visual |
|||||||||
|
S10.10.1 Table 10.11 |
LV3 |
Good Site Management · Large temporary stockpiles of excavated material shall be
covered with unobtrusive sheeting to prevent dust and dirt spreading to
adjacent landscape areas and vegetation, and to create a neat and tidy visual
appearance. · Construction plant and building material shall be orderly and
carefully stored in order to create a neat and tidy visual appearance. |
Minimize visual impact |
Contractor |
Within Project site |
Construction stage |
- |
· Implemented |
|
|
S10.10.1 Table 10.11 |
LV4 |
Screen Hoarding · Decorative screen hoarding should be erected to screen the
public from the construction area. It should be designed to be
compatible with the existing urban context. |
Minimize visual impact |
Contractor |
Within Project site |
Construction stage |
- |
· Implemented |
|
|
S10.10.1 Table 10.11 |
LV5 |
Lighting Control during
Construction · All lighting in the construction site shall be carefully
controlled to minimize light pollution and night-time glare to nearby residencies
and GIC. The Contractor shall consider other security measures, which
shall minimize the visual impacts. |
Minimize visual impact |
Contractor |
Within Project site |
Construction stage |
- |
· Implemented |
|
|
S10.10.1 Table 10.11 |
LV6 |
Erosion Control · The potential for soil erosion shall be reduced by minimizing
the extent of vegetation disturbance on site and by providing a protective
cover over newly exposed soil. |
Minimize landscape impact |
Contractor |
Within Project site |
Construction stage |
- |
· N/A |
|
|
S10.10.1 Table 10.11 |
LV7 |
Tree Protection &
Preservation · Carefully protected during construction. Tree protection
measures will be detailed at the Tree Removal Application stage and plans
submitted to the relevant Government Department for approval in due course in
accordance with ETWB TC no. 3/2006. |
Minimize landscape and visual impact |
Contractor |
Within Project site |
Construction stage |
· ‘Guidelines for Tree Risk Management and Assessment Arrangement on
an Area Basis and on a Tree Basis’, Greening, Landscape and Tree Management
(GLTM) Section, DEVB · Latest recommended horticultural practices from GLTM Section,
DEVB |
· Implemented |
|
|
S10.10.1 Table 10.11 |
LV8 |
Tree Transplantation · For trees unavoidably affected by the Project that have to be
removed, where practical transplantation will be chosen as the top priority
method of removal. If this is not possible or practical compensatory planting
will be provided for trees unavoidably felled (See LV10). For trees
unavoidably affected by the Project works that are transplanted,
transplantation must be carried out in accordance with ETWB TCW 2/2004 and
3/2006. |
Minimize landscape and visual impact |
Contractor |
Within Project site and designated off-site locations |
Prior to Construction stage |
· ETWB TCW 3/2006 · Latest recommended horticultural practices from Greening,
Landscape and Tree Management (GLTM) Section, DEVB · ETWB TCW 2/2004 |
· N/A |
|
|
S10.10.1 Table 10.11 |
LV9 |
Compensatory Planting · For trees unavoidably affected by the Project that have to be
removed, where practical transportation will be chosen as the top priority
method of removal but if this is not possible or practical compensatory
planting will be provided for trees unavoidably felled. All felled
trees shall be compensated for by planting trees to the satisfaction of
relevant Government projects. Required numbers and locations of
compensatory trees shall be determined and agreed separately with Government
during the Tree Felling Application process under ETWBTC 3/2006. · Compensatory tree planting may be incorporated into public open
spaces and along roadside amenity areas affected by the construction works
and therefore be part of the bigger wider planting plans. Onsite
compensation planting is preferred but if necessary, additional receptor
sites outside the Works Area shall be agreed separately with Government during
the Tree Felling Application process. |
Minimize visual impact and also enhance landscape |
Contractor |
Within Project site |
Construction stage |
· ETWB TCW 3/2006 · Latest recommended horticultural practices from Greening,
Landscape and Tree Management (GLTM) Section, DEVB · ETWB TCW 2/2004 |
· N/A |
|
|
Cultural
Heritage Impact (Construction Phase) |
|||||||||
|
S11.4.4 |
CH1 |
The contractor should be alerted during the construction on the possibility
of locating archaeological remains and as a precautionary measure, AMO shall
be informed immediately in case of discovery of antiquities or supposed
antiquities in the subject sites. |
To preserve any cultural heritage items which may be removed and
damaged by the excavation |
Contractor |
During construction works for cut and cover tunnels |
Construction stage |
· AMOs requirements |
· Implemented |
|
|
S12.6.1 |
CH3 |
· Protective covering should be provided for the buildings in the form
of plastic sheeting; · Buffer zones should be provided between the construction works
and the external walls of the buildings and should be as large as site
restrictions allow and be marked out by temporary fencing or hoarding; · An underpinning scheme is required to transfer the existing
column loadings to a deeper rock stratum. The supporting system includes
cutting the existing ground floor slab to expose the existing pile caps and
then construct transfer beams at both sides of the pile caps. The transfer
beams will tie up with the existing caps. Loadings of the transfer beams will
be transferred to the rock socket piles installed at the two ends of the
beams; · The AAA settlement and tilting limit should be 6/8/10 mm
and1/2000, 1/1500 and 1/1000; · Monitoring of vibration levels will be undertaken during the
construction phase and the Alert, Alarm and Action (AAA) vibration limit will
be set at 5/6/7.5 mm/s. The monitoring proposal should be sent to AMO for
comment;. · Regular site inspections and monitoring works will be carried
out by the contractor and the monitoring results will be submitted to the
resident site staff of HyD to ensure compliance. |
Protect the building
from damage from construction works |
Contractor |
Yau Ma Tei Police Station (Old Wing) (CKR-01) |
Prior to commencement of and during the construction phase |
· Guidelines for Cultural Heritage Impact Assessment · EIAO-TM Annex 10 and Annex 19 · AMO Proposed Vibration Limits |
· Implemented |
|
|
S12.6.1 |
|
· Adopting diaphragm wall construction method; · Grout curtain should be provided in front of the building; · Recharging system should be installed as a contingency measure
to mitigate the fluctuation of water table; · the AAA settlement and tilting limit should be 6/8/10 mm and
1/2000, 1/1500 and 1/1000; · Monitoring of vibration levels will be undertaken during the
construction phase and the Alert, Alarm and Action (AAA) vibration limit will
be set at 5/6/7.5 mm/s. The monitoring proposal should be sent to AMO for
comment;. · Regular site inspections and monitoring works will be carried
out by the contractor and the monitoring results will be submitted to the
resident site staff of HyD to ensure compliance. |
Protect the building
from damage from construction works |
Contractor |
Yau Ma Tei Police Station (Old Wing) (CKR-01) |
Prior to commencement of and during the construction phase |
· Guidelines for Cultural Heritage Impact Assessment · EIAO-TM Annex 10 and Annex 19 · AMO Proposed Vibration Limits |
· Implemented |
|
|
S12.6.1
Table 12.2 |
|
· The Alert, Alarm and Action (AAA) vibration limit will be set at
3/4/5 mm/s and a condition survey shall be carried out by the project
proponent prior to the construction phase to confirm this assessment · Vibration monitoring of the structure shall be employed during
the construction phase to ensure that the level is not exceeded. The
monitoring proposal should be sent to AMO for comment. |
Protect the building
from damage from construction works |
Contractor |
Tin Hau Temple (CKR-02) |
Prior to commencement of and during the construction phase |
· Guidelines for Cultural Heritage Impact Assessment · EIAO-TM Annex 10 and Annex 19 · AMO Proposed Vibration Limits |
· Implemented |
|
|
EM&A
Project |
|||||||||
|
S13.2 |
EM1 |
An Independent Environmental Checker needs to be employed as per
the EM&A Manual |
Control EM&A Performance |
Highways Department |
All construction sites |
Construction stage |
· EIAO Guidance Note No. 4/2010 · TM-EIAO |
· Implemented |
|
|
S13.2-13.4 |
EM2 |
· An Environmental Team needs to be employed as per the EM&A
Manual; · Prepare a systematic Environmental Management Plan to ensure
effective implementation of the mitigation measures; · An environmental impact monitoring needs to be implemented by
the Environmental Team to ensure all the requirements given in the EM&A
Manual are fully complied with. |
Perform environmental monitoring & auditing |
Highways Department/ Contractor |
All construction sites |
Construction stage |
· EIAO Guidance Note No. 4/2010 · TM-EIAO |
· Implemented |
|
Appendix G
Monitoring
Schedule of the Reporting Month
Appendix H
Calibration
Certificates
(Air
Monitoring)









Appendix I
Calibration
Certificates (Noise)








Appendix J
The
Certification of Laboratory with HOKLAS Accredited Analytical Tests

Appendix K
Location
Plan of Noise and Air Quality Monitoring Station

![]()
![]()
Appendix L
Monitoring
Data (Air Monitoring)
Location: |
Yau
Ma Tei Catholic Primary School (Hoi Wang Road) (W-A1) |
|
03,
09, 15, 21, 25 and 29 September 2026 |
|
|
Parameter: |
TSP
1-hour |
|
Other
Factors: |
Nearby
traffic |
|
Date |
1-hour
TSP (μg/m3) |
|||||
|
Weather |
Start
Time |
1st
Hour (μg/m3) |
2nd
Hour (μg/m3) |
3rd
Hour (μg/m3) |
||
|
2026-09-03 |
Sunny |
13:10 |
16 |
15 |
11 |
|
|
2026-09-09 |
Sunny |
11:06 |
12 |
11 |
8 |
|
|
2026-09-15 |
Cloudy |
14:30 |
12 |
7 |
7 |
|
|
2026-09-21 |
Cloudy |
09:25 |
28 |
16 |
17 |
|
|
2026-09-25 |
Sunny |
10:49 |
16 |
9 |
11 |
|
|
2026-09-29 |
Sunny |
8:36 |
24 |
13 |
5 |
|
|
Minimum: 5 μg/m3 |
Maximum: 28 μg/m3 |
|||||
Location: |
Man
Cheong Building (W-A6) |
|
Monitoring
date: |
03,
09, 15, 21, 25 and 29 September 2026 |
|
Parameter
: |
TSP
1-hour |
|
Other
Factors |
Nearby
traffic |
|
Date |
1-hour TSP (μg/m3) |
|||||
|
Weather |
Start Time |
1st Hour (μg/m3) |
2nd Hour (μg/m3) |
3rd Hour (μg/m3) |
||
|
2026-09-03 |
Sunny |
15:27 |
14 |
11 |
11 |
|
|
2026-09-09 |
Sunny |
15:24 |
16 |
11 |
15 |
|
|
2026-09-15 |
Cloudy |
12:42 |
16 |
11 |
7 |
|
|
2026-09-21 |
Cloudy |
13:08 |
21 |
19 |
19 |
|
|
2026-09-25 |
Sunny |
10:20 |
16 |
8 |
7 |
|
|
2026-09-29 |
Sunny |
13:39 |
18 |
19 |
15 |
|
|
Minimum:
7 μg/m3 |
Maximum:
21 μg/m3 |
|||||

Figure 1:
Graphical Illustration of Measured 1-hour TSP (μg/m3) Levels at
W-A1

Figure 2:
Graphical Illustration of Measured 1-hour TSP (μg/m3) Levels at
W-A6
|
Location: |
Yau Ma Tei Catholic Primary School (Hoi
Wang Road) (W-A1) |
|
Monitoring date: |
03, 09, 15, 21, 25 and 29 September 2026 |
|
Parameter : |
TSP 24-hour |
|
Other Factors |
Nearby traffic |
|
|
|

Location: |
Man
Cheong Building (W-A6) |
|
Monitoring
date: |
03,
09, 15, 21, 25 and 29 September 2026 |
|
Parameter
: |
TSP
24-hour |
|
Other
Factors |
Nearby
traffic |


Figure 3:
Graphical Illustration of Measured 24-hour TSP (μg/m3) Levels
at W-A1

Figure 4:
Graphical Illustration of Measured 24-hour TSP (μg/m3) Levels
at W-A6
Wind direction data for 03, 04, 09, 10, 15, 16, 21, 22,
25, 26, 29 and 30 September 2026












Wind speed data for
03, 04, 09, 10, 15, 16, 21, 22, 25, 26, 29 and 30 September 2026












Appendix M
Monitoring
Data (Noise)
Location: |
Yau
Ma Tei Catholic Primary School (Hoi Wang Road) (W-N1A) |
|
Monitoring
date: |
03,
09, 15, 21, 25 and 29 September 2026 |
|
Parameter
: |
Leq,
L10, L90 |
|
Other
Factors |
Nearby
traffic |
Noise
Monitoring data:
|
Date |
Weather |
Start Time |
- |
End Time |
Leq |
L10 |
L90 |
Wind speed (m/s) |
|
2026-09-03 |
Sunny |
13:07 |
- |
13:37 |
59.7 |
61.2 |
57.9 |
2.8 |
|
2026-09-09 |
Sunny |
11:03 |
- |
11:33 |
62.1 |
63.2 |
61.5 |
5.0 |
|
2026-09-15 |
Cloudy |
14:28 |
- |
14:58 |
59.0 |
60.4 |
57.8 |
0.7 |
|
2026-09-21 |
Cloudy |
9:03 |
- |
9:33 |
62.4 |
62.9 |
61.6 |
0.8 |
|
2026-09-25 |
Sunny |
10:35 |
- |
11:05 |
62.0 |
63.6 |
61.0 |
3.5 |
|
2026-09-29 |
Sunny |
8:23 |
- |
8:53 |
56.0 |
57.0 |
55.1 |
2.1 |
Remarks: Examinations
were not scheduled at Yau Ma Tei Catholic Primary School during the reporting
month. The limit level was 70 dB(A) in the reporting month.
Location: |
Hydan
Place (W-N18) |
|
Monitoring
date: |
03,
09, 15, 21, 25 and 29 September 2026 |
|
Parameter
: |
Leq,
L10, L90 |
|
Other
Factors |
Nearby
traffic |
Noise
Monitoring data:
|
Date |
Weather |
Start Time |
- |
End Time |
Leq |
L10 |
L90 |
Wind speed (m/s) |
|
2026-09-03 |
Sunny |
15:40 |
- |
16:10 |
61.5 |
64.1 |
59.6 |
2.8 |
|
2026-09-09 |
Sunny |
15:42 |
- |
16:12 |
63.5 |
66.1 |
61.6 |
3.6 |
|
2026-09-15 |
Cloudy |
13:00 |
- |
13:30 |
65.5 |
68.0 |
63.1 |
3.1 |
|
2026-09-21 |
Cloudy |
13:40 |
- |
14:10 |
61.8 |
64.4 |
59.8 |
2.2 |
|
2026-09-25 |
Sunny |
14:03 |
- |
14:33 |
61.3 |
64.1 |
59.2 |
3.9 |
|
2026-09-29 |
Sunny |
14:28 |
- |
14:58 |
62.0 |
64.7 |
60.0 |
3.3 |
Location: |
Prosperous
Garden Block 1 (W-N25A) |
|
Monitoring
date: |
03,
09, 15, 21, 25 and 29 September 2026 |
|
Parameter
: |
Leq,
L10, L90 |
|
Other
Factors |
Nearby
traffic |
Noise
Monitoring data:
|
Date |
Weather |
Start Time |
- |
End Time |
Leq |
L10 |
L90 |
Wind speed (m/s) |
|
2026-09-03 |
Sunny |
13:53 |
- |
14:23 |
65.3 |
67.9 |
63.2 |
3.9 |
|
2026-09-09 |
Sunny |
14:35 |
- |
15:05 |
62.8 |
75.9 |
60.8 |
3.5 |
|
2026-09-15 |
Cloudy |
11:13 |
- |
11:43 |
66.0 |
68.1 |
63.8 |
2.8 |
|
2026-09-21 |
Cloudy |
14:25 |
- |
14:55 |
66.6 |
71.6 |
64.0 |
1.4 |
|
2026-09-25 |
Sunny |
13:22 |
- |
13:52 |
65.1 |
67.8 |
63.0 |
4.2 |
|
2026-09-29 |
Sunny |
13:45 |
- |
14:15 |
66.6 |
68.6 |
64.9 |
3.3 |
Location: |
The
Coronation Tower 1 (W-P11) |
|
Monitoring
date: |
03,
09, 15, 21, 25 and 29 September 2026 |
|
Parameter
: |
Leq,
L10, L90 |
|
Other
Factors |
Nearby
traffic |
Noise
Monitoring data:
|
Date |
Weather |
Start Time |
- |
End Time |
Leq |
L10 |
L90 |
Wind speed (m/s) |
|
Sunny |
14:43 |
- |
15:13 |
65.6 |
67.1 |
64.1 |
3.9 |
|
|
2026-09-09 |
Sunny |
13:22 |
- |
13:52 |
66.1 |
68.9 |
63.9 |
4.2 |
|
2026-09-15 |
Cloudy |
15:20 |
- |
15:50 |
65.8 |
68.4 |
63.7 |
2.9 |
|
2026-09-21 |
Cloudy |
16:31 |
- |
17:01 |
65.8 |
67.9 |
63.9 |
2.8 |
|
2026-09-25 |
Sunny |
11:17 |
- |
11:47 |
64.2 |
65.7 |
63.1 |
3.6 |
|
2026-09-29 |
Sunny |
16:05 |
- |
16:35 |
66.4 |
68.0 |
64.9 |
4.6 |
Figure 1:
Graphical Illustration of Measured Noise Levels at W-N1A

Figure 2:
Graphical Illustration of Measured Noise Levels at W-N18
Figure 3:
Graphical Illustration of Measured Noise Levels at W-N25A

Figure 4:
Graphical Illustration of Measured Noise Levels at W-P11
Appendix N
Waste
Flow Table
Monthly Summary
Waste Flow Table
Name of Department:
Highways Department
Contract No. / Works Order No.: __HY/2014/08__
Monthly Summary
Waste Flow Table for September 2026
[to be submitted not later than the
15th day of each month following reporting month] (All
quantities shall be rounded off to 2 decimal places.)
|
Month |
|
Actual Quantities of Inert Construction
Waste Generated Monthly |
||||||||||||
|
(a)=(b)+(c)+(d)+(e)+
(f)+ (g)+ (h)+ (i)+ (j)+ (k) Total
Quantity Generated |
(b) Hard
Rock and Large Broken Concrete |
(c) Reused
in the Contract |
(d) Reused
in other Projects |
(e) Disposed
of as Public Fill |
(f) Imported
Fill |
|||||||||
|
(in
‘tonnes) |
(in
‘tonnes) |
(in
‘tonnes) |
(in
‘tonnes) |
(in
‘tonnes) |
(in
‘tonnes) |
|||||||||
|
Jan-26 |
2368.70 |
1505.70 |
0.00 |
0.00 |
695.80 |
0.00 |
||||||||
|
Feb-26 |
644.40 |
80.00 |
0.00 |
0.00 |
507.00 |
0.00 |
||||||||
|
Mar-26 |
1288.60 |
525.50 |
0.00 |
0.00 |
713.50 |
0.00 |
||||||||
|
Apr-26 |
1864.90 |
839.70 |
0.00 |
0.00 |
961.60 |
0.00 |
||||||||
|
May-26 |
422.70 |
93.60 |
0.00 |
0.00 |
272.20 |
0.00 |
||||||||
|
Jun-26 |
1017.20 |
256.10 |
0.00 |
0.00 |
704.90 |
0.00 |
||||||||
|
Sub-total |
7606.50 |
3300.60 |
0.00 |
0.00 |
3855.00 |
0.00 |
||||||||
|
Jul-26 |
954.20 |
335.80 |
0.00 |
0.00 |
557.10 |
0.00 |
||||||||
|
Aug-26 |
761.40 |
272.10 |
0.00 |
0.00 |
454.00 |
0.00 |
||||||||
|
Sep-26 |
607.20 |
238.30 |
0.00 |
0.00 |
344.20 |
0.00 |
||||||||
|
Oct-26 |
|
|
|
|
|
|
||||||||
|
Nov-26 |
|
|
|
|
|
|
||||||||
|
Dec-26 |
|
|
|
|
|
|
||||||||
|
Total |
9929.30 |
4146.80 |
0.00 |
0.00 |
5210.30 |
0.00 |
||||||||
|
2018 |
51057.90 |
0.00 |
0.00 |
0.00 |
47715.60 |
2877.40 |
||||||||
|
2019 |
112830.10 |
541.00 |
1523.80 |
13525.00 |
93132.90 |
3155.60 |
||||||||
|
2020 |
193021.92 |
58778.00 |
1205.60 |
19108.60 |
112556.80 |
0.00 |
||||||||
|
2021 |
104679.02 |
6461.30 |
1393.70 |
1144.70 |
92950.20 |
1542.90 |
||||||||
|
2022 |
114787.22 |
3600.50 |
1804.50 |
18471.20 |
90202.70 |
0.00 |
||||||||
|
2023 |
192946.67 |
73219.70 |
1670.00 |
20008.60 |
96991.50 |
0.00 |
||||||||
|
2024 |
282726.21 |
52152.28 |
25269.83 |
70408.56 |
128027.11 |
4773.80 |
||||||||
|
2025 |
127420.17 |
4843.90 |
343.10 |
1156.60 |
8134.90 |
110817.60 |
||||||||
|
Accumulated
Total |
1189398.51 |
203743.48 |
33210.53 |
143823.26 |
674922.01 |
123167.30 |
||||||||
Month |
Actual Quantities of Non-inert
Construction Waste Generated Monthly |
|||||||||||||
|
(g) Metals |
(h) Paper/
cardboard packaging |
(i) Plastics |
(j) Chemical
Waste |
(k) Others, e.g. General Refuse disposed at Landfill |
||||||||||
|
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in
‘tonnes) |
||||||||||
|
generated |
recycled |
generated |
recycled |
generated |
recycled |
generated |
recycled |
generated |
||||||
|
Jan-26 |
0.00 |
0.00 |
0.00 |
1.00 |
0.00 |
0.00 |
0.00 |
0.00 |
166.20 |
|||||
|
Feb-26 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
57.40 |
|||||
|
Mar-26 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
49.60 |
|||||
|
Apr-26 |
0.00 |
0.00 |
0.00 |
1.30 |
0.00 |
0.00 |
0.00 |
0.00 |
62.30 |
|||||
|
May-26 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
56.90 |
|||||
|
Jun-26 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
56.20 |
|||||
|
Sub-total |
0.00 |
0.00 |
0.00 |
2.30 |
0.00 |
0.00 |
0.00 |
0.00 |
448.60 |
|||||
|
Jul-26 |
0.00 |
0.00 |
0.00 |
0.40 |
0.00 |
0.00 |
0.00 |
0.00 |
60.90 |
|||||
|
Aug-26 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
35.30 |
|||||
|
Sep-26 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
24.70 |
|||||
|
Oct-26 |
|
|
|
|
|
|
|
|
|
|||||
|
Nov-26 |
|
|
|
|
|
|
|
|
|
|||||
|
Dec-26 |
|
|
|
|
|
|
|
|
|
|||||
|
Total |
0.00 |
0.00 |
0.00 |
2.70 |
0.00 |
0.00 |
0.00 |
0.00 |
569.50 |
|||||
|
2018 |
28.40 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
2.00 |
0.00 |
434.50 |
|||||
|
2019 |
0.00 |
9.10 |
3.40 |
6.80 |
0.00 |
0.00 |
5.20 |
0.00 |
927.30 |
|||||
|
2020 |
69.20 |
0.00 |
3.30 |
0.00 |
0.02 |
0.00 |
25.30 |
0.00 |
1275.10 |
|||||
|
2021 |
30.20 |
0.00 |
4.80 |
0.00 |
0.02 |
0.00 |
25.50 |
0.00 |
1125.70 |
|||||
|
2022 |
108.60 |
0.00 |
3.30 |
0.40 |
0.02 |
0.00 |
1.20 |
0.00 |
594.80 |
|||||
|
2023 |
0.00 |
65.70 |
0.00 |
2.71 |
0.00 |
0.06 |
0.00 |
0.00 |
988.40 |
|||||
|
2024 |
0.00 |
143.41 |
0.00 |
5.28 |
0.00 |
0.81 |
0.00 |
4.00 |
1941.13 |
|||||
|
2025 |
0.00 |
662.90 |
0.00 |
2.46 |
0.00 |
0.01 |
0.00 |
0.00 |
1458.70 |
|||||
|
|
236.40 |
881.11 |
14.80 |
20.35 |
0.06 |
0.88 |
59.20 |
4.00 |
9315.13 |
|||||
Appendix O
Statistics on Complaint, Notifications of
Summons and Successful Prosecutions
Statistical
Summary of Exceedances
|
Air
Quality |
||
|
Reporting
Period |
Action
Level |
Limit
Level |
|
1
– 30 September 2026 |
0 |
0 |
|
Noise |
||
|
Reporting
Period |
Action
Level |
Limit
Level |
|
1
– 30 September 2026 |
1 |
0 |
Statistical
Summary of Environmental Complaints
|
Reporting
Period |
Environmental
Complaint Statistics |
||
|
Frequency
|
Cumulative |
Complaint
Nature |
|
|
1
– 30 September 2026 |
1 |
203 |
Noise
Impact |
Statistical
Summary of Environmental Non-compliance
|
Reporting
Period |
Environmental
Non-compliance Statistics |
||
|
Frequency
|
Cumulative |
Details |
|
|
1
– 30 September 2026 |
0 |
2 |
N/A |
Statistical
Summary of Environmental Summons
|
Reporting
Period |
Environmental
Summons Statistics |
||
|
Frequency
|
Cumulative |
Details |
|
|
1
– 30 September 2026 |
0 |
1 |
N/A |
Statistical
Summary of Environmental Prosecution
|
Reporting
Period |
Environmental
Prosecution Statistics |
||
|
Frequency
|
Cumulative |
Details |
|
|
1
– 30 September 2026 |
0 |
0 |
N/A |
Appendix P
Monitoring Schedule of the Coming Month

Appendix Q
Interim Report for the Complaint










3 Air Quality and Noise
Monitoring
6 Summary of Complaints,
Notification of Summons and Prosecutions
9 Conclusion and
Recommendations
Appendices
Appendix A Alignment and Works
Site in Yau Ma Tei West Area for Contract No. HY/2023/08
Appendix
B Construction Programme
Appendix
C Project Organization Chart
Appendix
D Event and Action Plan (EAP)
(Air Quality Monitoring)
Appendix E
Event and Action Plan (EAP) (Noise
Monitoring)
Appendix
F Environmental Mitigation
Implementation Schedule (EMIS)
Appendix
G Waste Flow Table
Appendix
H Statistics on Complaint,
Notifications of Summons and Successful Prosecutions
|
Construction Activities Undertaken in Yau Ma Tei West |
|
·
Architectural Builder's Works and Finishes (ABWF) and E&M Works at
Management Office Building (Portion of Site Part 1D) ·
Reinforced concrete works for Toilet Building (Portion of Site 1D) ·
Retaining wall and planter wall construction at YMTW at-grade (Portion
of Site Part 1D) ·
Drainage works and underground ducting at YMTW at-grade (Portion of
Site Part 1D) ·
Construction of Staff Office and Toilet Building (Portion of Site Part
3A, 3B & 3C) ·
Drainage works, box culvert modification and U-Channel installation at
North Tree Park Area (Portion of Site Part 3A, 3B & 3C) ·
Underground cable ducting for E&M works (Portion of Site Part 3A,
3B & 3C) ·
Superstructure (column, wall & upper slab) construction at Jade
Hawker Bazaar – Block A (Portion of Site Part 7A) ·
ABWF and E&M Works at Jade Hawker Bazaar – Block A (Portion of
Site Part 7A) ·
External finishes at Jade Hawker Bazaar – Block A (Portion of Site
Part 7A) ·
Superstructure (column, wall & upper slab) construction at Jade
Hawker Bazaar – Block B (Portion of Site Part 7B) ·
ABWF and E&M Works at Jade Hawker Bazaar – Block B (Portion of
Site Part 7B) ·
External finishes at Jade Hawker Bazaar – Block B (Portion of Site
Part 7B) ·
Reinforced concrete works and cable ducting for lighting System at
Rest Garden – D |
- No
Action / Limit Level exceedance for 1-hour TSP was recorded.
- No
Action / Limit Level exceedance for 24-hour TSP was recorded.
-
No Limit Level exceedance for noise monitoring was recorded.
-
No Limit Level exceedance for noise monitoring was recorded.
|
Construction Activities To be Undertaken in Yau Ma Tei West Area |
|
· ABWF
and E&M works at Maintenance Office Building (Portion of the Site Part
1D) ·
Reinforced concrete works for Toilet Building (Portion of the Site 1D) ·
Retaining wall and planter wall construction at YMTW at-grade (Portion
of the Site Part 1D) · Drainage
works and underground ducting at YMTW at-grade (Portion of Site Part 1D) ·
Construction of Staff Office and Toilet Building (Portion of Site Part
3A, 3B & 3C) ·
Drainage works, U-channel,
ducting and reinforced concrete works for boundary fence, kerb and footpath
at North Tree Park Area (Portion of Site Part 3A, 3B & 3C) ·
ABWF and E&M works at Jade Hawker Bazaar – Block A and B (Portion
of the Site Part 7A and 7B) ·
Ground slab construction and drainage works at Jade Hawker Bazaar –
Block B (Portion of the Site Part 7A and 7B) ·
External finishes at Jade Hawker Bazaar – Block A and B (Portion of
Site Part 7A and 7B) ·
Reinforced concrete works and cable ducting for lighting System at
Rest Garden – D |
Table
1.1
Summary of Construction Activities during the Reporting Period
|
Construction
Activities Undertaken in Yau Ma Tei West Area |
Progress |
|
·
ABWF and E&M Works at Management Office Building (Portion of Site
Part 1D) |
20% |
|
·
Reinforced concrete works for Toilet Building (Portion of Site 1D) |
90% |
|
·
Retaining wall and planter wall construction at YMTW at-grade (Portion
of Site Part 1D) |
87% |
|
·
Drainage works and underground ducting at YMTW at-grade (Portion of
Site Part 1D) |
36% |
|
·
Construction of Staff Office and Toilet Building (Portion of Site Part
3A, 3B & 3C) |
75% |
|
·
Drainage works, box culvert modification and U-Channel installation at
North Tree Park Area (Portion of Site Part 3A, 3B & 3C) |
36% |
|
·
Underground cable ducting for E&M works (Portion of Site Part 3A,
3B & 3C) |
5% |
|
·
Superstructure (column, wall & upper slab) construction at Jade
Hawker Bazaar – Block A (Portion of Site Part 7A) |
100% |
|
·
ABWF and E&M Works at Jade Hawker Bazaar – Block A (Portion of
Site Part 7A) |
30% |
|
·
External finishes at Jade Hawker Bazaar – Block A (Portion of Site
Part 7A) |
20% |
|
·
Superstructure (column, wall & upper slab) construction at Jade
Hawker Bazaar – Block B (Portion of Site Part 7B) |
99% |
|
·
ABWF and E&M Works at Jade Hawker Bazaar – Block B (Portion of
Site Part 7B) |
5% |
|
·
External finishes at Jade Hawker Bazaar – Block B (Portion of Site
Part 7B) |
25% |
|
·
Reinforced concrete works and cable ducting for lighting System at
Rest Garden – D |
30% |
Table 1.2 Contact Information of Key
Personnel
|
Party |
Role |
Position |
Name |
Contact No. |
|
|
Arup
– Mott MacDonald Joint Venture |
Engineer’s
Representative (“ER”) |
Resident
Engineer (Environmental) |
Ms.
Jim Li |
9120
1157 |
|
|
ERM
– Hong Kong Limited |
Independent
Environmental Checker (“IEC”) |
IEC |
Ms.
Mandy To |
2271
3313 |
|
|
Aurecon
Hong Kong Limited |
Environmental
Team (“ET”) |
ET
Leader |
Mr.
F. C. Tsang |
3664
6801 |
|
|
Build
King – Tung Lee Joint Venture |
Contractor |
Environmental
Officer |
Mr.
Tony Tsoi |
9689
8956 |
|
Table 1.3 Summary of the Environmental
Licence, Notification, Permit and Documentations
|
Permit/ License/ Notification / Reference No. |
Valid Period |
Status |
Remark |
|
|
From |
To |
|
|
|
|
Environmental Permit |
||||
|
EP-457/2013/D |
15
June 2021 |
-- |
Valid |
-- |
|
Wastewater Discharge
License |
||||
|
WT00048838-2026 |
6
July 2026 |
End
of Project |
Valid |
For
North Tree Park |
|
WT00048837-2026 |
6
July 2026 |
End
of Project |
Valid |
For
Jade Hawker Bazaar |
|
WT00048926-2026 |
24
July 2026 |
End
of Project |
Valid |
For
At-Grade Yau Ma Tei Landscaped Deck |
|
Notification of
Construction Works Under the Air Pollution Control (Construction Dust
Regulation) |
||||
|
10007351,
10007352 |
25
July 2024 |
End
of Project |
Notified |
-- |
|
Chemical Waste Producer
Registration |
||||
|
5213-252-B2767-01 |
14
August 2024 |
-- |
Valid |
-- |
|
Billing Account for
Disposal of Construction Waste |
||||
|
7051793 |
6
August 2024 |
-- |
Valid |
-- |
|
Y-Park Membership |
||||
|
C0280 |
12
August 2024 |
-- |
Valid |
-- |
|
Construction Nosie Permit |
||||
|
GW-RE0743-26 |
21
July 2026 |
31
December 2026 |
Valid |
General
Activities at Yau Ma Tei Landscaped Deck |
|
GW-RE0744-26 |
21
July 2026 |
31
December 2026 |
Valid |
General
Activities at At-Grade Yau Ma Tei Landscaped Deck |
|
GW-RE0745-26 |
21
July 2026 |
31
December 2026 |
Valid |
General
Activities at North Tree Park |
|
GW-RE0671-26 |
02
July 2026 |
31
December 2026 |
Valid |
General
Activities at Jade Hawker Bazaar |
|
GW-RE0844-26 |
18
August 2026 |
17
November 2026 |
Valid |
Reinstatement
Works of foul drain connection of the Jade Hawker Bazaar |
Table
2.1 Summary of Status of Required
Submission for EP-457/2013/D for the Project
|
EP
Condition |
Submission |
Submission Date |
|
3.4 |
Monthly EM&A
Report – Yau Ma Tei West Area (August 2026) |
14
September 2026 |
Table
4.1 Quantities of Waste Generated from the
Project in the Reporting Period
|
Reporting period |
Quantity |
|||||
|
Inert
C&D Materials (in
‘000 kg) |
Chemical
Waste (in
‘kg) |
Non-inert
C&D Materials |
||||
|
Others,
e.g. General Refuse disposed of at Landfill (in
‘000kg) |
Recycled
materials |
|||||
|
Paper/ cardboard (in
‘000kg) |
Plastics (in
‘000 kg) |
Metals (in
‘000 kg) |
||||
|
September
2026 |
1,204.070 |
0.000 |
78.900 |
0.000 |
0.000 |
0.000 |
|
Complaint
Received via Project Hotline |
Complaint Received via 1823 or from
other government departments |
||||
|
|
|
|
|
||
|
Contractor
notify ER, ET and IEC |
ER
notify Contractor, ET and IEC |
||||
|
|
|
|
|
||
|
Contractor
log complaint and date of receipt onto the complaint database. Contractor, ER
and ET to conduct investigation of complaint |
|||||
|
|
|
|
|
||
|
If
complaint is considered not valid |
If
complaint is found valid |
||||
|
|
|
|
|
||
|
ET
or ER to reply to the complainant if necessary |
Contractor to identify and implement remedial
measures in consultation with the IEC, ET and ER. |
||||
|
|
|
|
|
||
|
|
|
The ER, ET and IEC to review the effectiveness of
the Contractor’s remedial measures and the updated situation; ET to undertake
additional monitoring and audit to verify the situation if necessary and
oversee that circumstances leading to the complaint do not recur. ER to
conduct further inspection as necessary. |
|||
|
|
|
|
|
||
|
If
the complaint is referred by the EPD, the Contractor to prepare interim
report on the status of the complaint investigation and follow-up actions
stipulated above, including the details of the remedial measures and
additional monitoring identified or already taken, for submission to EPD
within the timeframe assigned by the EPD |
|||||
|
|
|
|
|||
|
The
ET to record the details of the complaint, results of the investigation,
subsequent actions taken to address the complaint and updated situation
including the effectiveness of the remedial measures, supported by regular
and additional monitoring results in the monthly EM&A reports |
|||||
Table 7.1 Summary of Site Observation
|
Date |
Environmental Observations |
Follow-up Status |
|
4 September 2026 |
1. At JHB (Block A), remediation action should be taken for the
chemical spillage observed. |
1. Chemical in concern was
removed. The concrete curing agent spill was cleaned up. (Rectified on 10
September 2026) |
|
|
2. At JHB (Block A),chemicals should be stored in drip tray(s) to
avoid leakage. |
2. Chemical in concern was removed. (Rectified on 10 September 2026) |
|
|
3. At JHB (Block B), general refuse should be kept in enclosed bin and
removed regularly. |
3. Housekeeping was enhanced. (Rectified on 10 September 2026) |
|
11 September 2026 |
Nil. |
Nil. |
|
17 September 2026 |
1. At JHB (Block B), drip tray(s) should be provided to chemicals to
avoid leakage. |
1.
Chemical in concern was removed. (Rectified on 23 September 2026) |
|
25 September 2026 |
Nil. |
Nil. |
|
Construction
Activities To be Undertaken in Yau Ma Tei West Area |
|
· ABWF
and E&M works at Maintenance Office Building (Portion of the Site Part
1D) ·
Reinforced concrete works for Toilet Building (Portion of the Site 1D) ·
Retaining wall and planter wall construction at YMTW at-grade (Portion
of the Site Part 1D) · Drainage
works and underground ducting at YMTW at-grade (Portion of Site Part 1D) ·
Construction of Staff Office and Toilet Building (Portion of Site Part
3A, 3B & 3C) ·
Drainage works, U-channel,
ducting and reinforced concrete works for boundary fence, kerb and footpath
at North Tree Park Area (Portion of Site Part 3A, 3B & 3C) ·
ABWF and E&M works at Jade Hawker Bazaar – Block A and B (Portion
of the Site Part 7A and 7B) ·
Ground slab construction and drainage works at Jade Hawker Bazaar –
Block B (Portion of the Site Part 7A and 7B) ·
External finishes at Jade Hawker Bazaar – Block A and B (Portion of
Site Part 7A and 7B) ·
Reinforced concrete works and cable ducting for lighting System at
Rest Garden – D |
Appendix
A
Alignment
and Works Site in Yau Ma Tei West Area for Contract No. HY/2023/08

f
Appendix
B
Construction
Programme
Appendix
C
Project Organisation Chart

Appendix
D
Event and Action Plan (EAP) (Air Quality Monitoring)
EVENT |
ACTION |
|||
|
ENVIRONMENTAL
TEAM (ET) |
INDEPENDENT
ENVIRONMENTAL CHECKER (IEC) |
ENGINEER’S
REPRESENTATIVE (ER) |
CONTRACTOR |
|
|
ACTION LEVEL |
||||
|
Exceedance for one
sample |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Inform IEC and
ER; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method. |
1. Notify Contractor. |
1. Rectify any unacceptable practice; 2. Amend working methods if appropriate. |
|
Exceedance for two
or more consecutive samples |
1. Identify
source; 2. Inform IEC and
ER; 3. Advise the ER
on the effectiveness of the proposed remedial measures; 4. Repeat
measurements to confirm findings; 5. Increase
monitoring frequency to daily; 6. Discuss with
IEC and Contractor on remedial actions required; 7. If exceedance
continues, arrange meeting with IEC and ER; 8. If exceedance
stops, cease additional monitoring. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss with ET
and Contractor on possible remedial measures; 4. Advise the ET
on the effectiveness of the proposed remedial measures; 5. Supervise
implementation of remedial measures. |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. Ensure remedial
measures properly implemented. |
1. Submit proposals for remedial actions to ER
within 3 working days of notification; 2. Implement the agreed proposals; 3. Amend proposal if appropriate. |
|
LIMIT LEVEL |
||||
|
Exceedance for one
sample |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Inform ER,
Contractor and EPD; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily; 5. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss with ET
and Contractor on possible remedial measures; 4. Advise the ER
on the effectiveness of the proposed remedial measures; 5. Supervise
implementation of remedial measures. |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. Ensure remedial
measures properly implemented. |
1. Take immediate action to avoid further
exceedance; 2. Submit proposals for remedial actions to
IEC within 3 working days of notification; 3. Implement the agreed proposals; 4. Amend proposal if appropriate. |
|
Exceedance for two
or more consecutive samples |
1. Notify IEC, ER,
Contractor and EPD; 2. Identify
source; 3. Repeat
measurement to confirm findings; 4. Increase
monitoring frequency to daily; 5. Carry out
analysis of Contractor’s working procedures to determine possible mitigation
to be implemented; 6. Arrange meeting
with IEC and ER to discuss the remedial actions to be taken; 7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results; 8. If exceedance
stops, cease additional monitoring. |
1. Discuss amongst
ER, ET, and Contractor on the potential remedial actions; 2. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; 3. Supervise the
implementation of remedial measures. |
1. Confirm receipt of notification of failure
in writing; 2. Notify Contractor; 3. In consultation with the IEC, agree with
the Contractor on the remedial measures to be implemented; 4. Ensure remedial measures properly
implemented; 5. If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated. |
1. Take immediate action to avoid further
exceedance; 2. Submit proposals for remedial actions to
IEC within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not
under control; 5. Stop the relevant portion of works as
determined by the ER until the exceedance is abated. |
Appendix
E
Event and Action Plan (EAP) (Noise Monitoring)
EVENT |
ACTION |
|||
|
ENVIRONMENTAL TEAM (ET) |
INDEPENDENT
ENVIRONMENTAL CHECKER (IEC) |
ENGINEER’S REPRESENTATIVE ER |
CONTRACTOR |
|
|
Action Level |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Notify IEC and
Contractor; 3. Report the
results of investigation to the IEC, ER and Contractor; 4. Discuss with
the Contractor and formulate remedial measures; 5. Increase
monitoring frequency to check mitigation effectiveness. |
1. Review the
analysed results submitted by the ET; 2. Review the
proposed remedial measures by the Contractor and advise the ER accordingly; 3. Supervise the
implementation of remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify
Contractor; 3. Require
Contractor to propose remedial measures for the analysed noise problem; 4. Ensure
remedial measures are properly implemented |
1. Submit noise
mitigation proposals to IEC; 2. Implement
noise mitigation proposals. |
Appendix
F
Environmental
Mitigation Implementation Schedule (EMIS)
Environmental
Mitigation Implementation Schedule
|
EIA
Ref. |
EM&A
Log Ref. |
Recommended
Mitigation Measures |
Objectives
of the Recommended Measures & Main Concerns to address |
Implementation
Agent |
Location
/ Timing |
Implementation
Stage |
Requirements
and/ or standards to be achieved |
Implementation
Status |
|
|
Construction Dust Impact |
|||||||||
|
S4.3.10 |
D1 |
The
contractor shall follow the procedures and requirements given in the Air
Pollution Control (Construction Dust) Regulation and Air Pollution Control
(Non-road Mobile Machinery) (Emission) Regulation. |
Minimize
dust impact and adverse health effects at the nearby sensitive receivers |
Contractor |
All construction
sites |
Construction
stage |
· APCO · To
control the dust impact to meet HKAQO and TM-EIA criteria |
Implemented after
reminder. |
|
|
S4.3.10 |
D2 |
· Mitigation
measures in form of regular watering under a good site practice should be
adopted. Watering once per hour on exposed worksites and haul road
should be conducted to achieve dust removal efficiencies of 91.7%. While the
above watering frequencies are to be followed, the extent of watering may
vary depending on actual site conditions but should be sufficient to maintain
an equivalent intensity of no less than 1.3 L/m2 to achieve the
dust removal efficiency. |
Minimize
dust impact at the nearby sensitive receivers |
Contractor |
All construction
sites |
Construction
stage |
· APCO · To control the
dust impact to meet HKAQO and TM-EIA criteria |
Implemented. |
|
|
S4.3.10 |
D3 |
· Proper
watering at exposed spoil should be undertaken throughout the construction
phase; · Any
excavated or stockpile of dusty material should be covered entirely by
impervious sheeting or sprayed with water to maintain the entire surface wet
and then removed or backfilled or reinstated where practicable within 24
hours of the excavation or unloading; · Any
dusty materials remaining after a stockpile is removed should be wetted with
water and cleared from the surface of roads; · A
stockpile of dusty material should not be extended beyond the pedestrian
barriers, fencing or traffic cones; · The
load of dusty materials on a vehicle leaving a construction site should be
covered entirely by impervious sheeting to ensure that the dusty materials do
not leak from the vehicle. · Where
practicable, vehicle washing facilities with high pressure water jet should
be provided at every discernible or designated vehicle exit point. The
area where vehicle washing takes place and the road section between the
washing facilities and the exit point should be paved with concrete,
bituminous materials or hardcores; · When
there are open excavation and reinstatement works, hoarding of not less than
2.4m high should be provided and properly maintained as far as practicable
along the site boundary with provision for public crossing. Good site
practice shall also be adopted by the Contractor to ensure the conditions of
the hoardings are properly maintained throughout the construction period; · The
portion of any road leading only to construction site that is within 30m of a
vehicle entrance or exit should be kept clear of dusty materials; · Surfaces
where any pneumatic or power-driven drilling, cutting, polishing or other
mechanical breaking operation takes place should be sprayed with water or a
dust suppression chemical continuously; · Any
area that involves demolition activities should be sprayed with water or a
dust suppression chemical immediately prior to, during and immediately after
the activities so as to maintain the entire surface wet; · Any
skip hoist for material transport should be totally enclosed by impervious
sheeting; · Every
stock of more than 20 bags of cement or dry-pulverised fuel ash (PFA) should
be covered entirely by impervious sheeting or placed in an area sheltered on
the top and the 3 sides; · Loading,
unloading, transfer, handling or storage of bulk cement or dry PFA should be
carried out in a totally enclosed system or facility, and any vent or exhaust
should be fitted with an effective fabric filter or equivalent air pollution
control system · Exposed
earth should be properly treated by compaction, turfing, hydroseeding,
vegetation planting or sealing with latex, vinyl, bitumen, shotcrete or other
suitable surface stabilizer within six months after the last construction
activity on the construction site or part of the construction site where the
exposed earth lies. |
Minimize
dust impact at the nearby sensitive receivers |
Contractor |
All construction
sites |
Construction
stage |
· APCO · To control the
dust impact to meet HKAQO and TM-EIA criteria |
Implemented for
the 1st to 8th, 12th and 14th
bullets. N/A for
other bullets. |
|
|
S4.3.10 |
D6 |
Implement
regular dust monitoring under EM&A programme during the construction
stage. |
Monitoring of
dust impact |
Contractor |
Selected rep.
dust monitoring station |
Construction
stage |
· TM-EIA |
Implemented |
|
|
Construction
Noise (Airborne) |
|||||||||
|
S5.4.1 |
N1 |
Implement the following good site practices: · Only
well-maintained plant should be operated on-site, and plant should be
serviced regularly during the construction programme; · Machines and
plant (such as trucks, cranes) that may be in intermittent use should be shut
down between work periods or should be throttled down to a minimum; · Plant known to
emit noise strongly in one direction, where possible, be orientated so that
the noise is directed away from nearby NSRs; · Silencers or
mufflers on construction equipment should be properly fitted and maintained
during the construction works; · Mobile plant
should be sited as far away from NSRs as possible and practicable; · Material
stockpiles, mobile container site office and other structures should be
effectively utilized, where practicable, to screen noise from on-site
construction activities. |
Control
construction airborne noise |
Contractor |
All construction
sites |
Construction
stage |
· Annex 5, TM-EIAO |
Implemented for
the 1st, 2nd, 5th bullets, N/A for other
bullets |
|
|
S5.4.1 |
N2 |
Install
temporary hoarding located on the site boundaries between noisy construction
activities and NSRs. The conditions of hoardings shall be properly
maintained throughout the construction period. |
Reduce the construction noise levels at low-level zone of NSRs through
partial screening |
Contractor |
All construction sites |
Construction stage |
· Annex 5, TM-EIAO |
Implemented |
|
|
S5.4.1 |
N3 |
Install
movable noise barriers (typical design is wooden framed barrier with a
small-cantilevered on a skid footing with 25mm thick internal sound
absorptive lining), acoustic mat or full enclosure, screen the noisy plants
including air compressors, generators and handheld breakers, etc. |
Screen the noisy plant items to be used at all construction sites |
Contractor |
All construction sites where practicable |
Construction stage |
· Annex 5, TM-EIAO |
Implemented |
|
|
S5.4.1 |
N4 |
Use ‘Quiet plant’ |
Reduce the noise levels of plant items |
Contractor |
All construction sites where practicable |
Construction stage |
· Annex 5, TM-EIAO |
Implemented |
|
|
S5.4.1 |
N5 |
Loading/
unloading activities should be carried out inside the full enclosure of
mucking out points. |
Reduce the noise levels of loading/ unloading activities |
Contractor |
Mucking out locations |
Construction stage |
· Annex 5, TM-EIAO |
N/A |
|
|
S5.4.1 |
N6 |
Sequencing
operation of construction plants where practicable. |
Operate sequentially within the same work site to reduce the
construction airborne noise |
Contractor |
All construction sites where practicable |
Construction stage |
· Annex 5, TM-EIAO |
N/A |
|
|
S5.4.1 |
N7 |
Implement
a noise monitoring programme under EM&A programme. |
Monitor the construction noise levels at the selected representative
locations |
Contractor |
Selected rep. noise monitoring station |
Construction stage |
· TM-EIAO |
Implemented |
|
|
Water
Quality (Construction Phase) |
|||||||||
|
S6.9.1.1 |
W1 |
In
accordance with the Practice Note for Professional Persons on Construction
Site Drainage, Environmental Protection Department, 2023 (ProPECC PN 2/23),
construction phase mitigation measures shall include the following: Construction
Runoff · At the start of
site establishment, perimeter cut-off drains to direct off-site water around
the site should be constructed with internal drainage works and erosion and
sedimentation control facilities implemented. Channels (both temporary
and permanent drainage pipes and culverts), earth bunds or sandbag barriers
should be provided on site to direct stormwater to silt removal
facilities. The design of the temporary on-site drainage system will be
undertaken by the contractor prior to the commencement of construction; · The dikes or
embankments for flood protection should be implemented around the boundaries
of earthwork areas. Temporary ditches should be provided to facilitate
the runoff discharge into an appropriate watercourse, through a silt/
sediment trap. The sediment/ silt traps should be incorporated in the
permanent drainage channels to enhance deposition rates; · The design of
efficient silt removal facilities should be based on the guidelines in
Appendix A1 of ProPECC PN 2/23, which states that the retention time for
silt/ sand traps should be 5 minutes under maximum flow conditions.
Sizes may vary depending upon the flow rate, but for a flow rate of 0.1 m3/s
a sedimentation basin of 30 m3 would be required and for a flow
rate of 0.5 m3/s the basin would be 150 m3. The
detailed design of the sand/ silt traps shall be undertaken by the contractor
prior to the commencement of construction; · All exposed earth
areas should be completed and vegetated as soon as possible after earthworks
have been completed, or alternatively, within 14 days of the cessation of
earthworks where practicable. Exposed slope surfaces should be covered
by tarpaulin or other means; · The overall slope
of the site should be kept to a minimum to reduce the erosive potential of
surface water flows, and all traffic areas and access roads protected by
coarse stone ballast. An additional advantage accruing from the use of
crushed stone is the positive traction gained during prolonged periods of
inclement weather and the reduction of surface sheet flows; · All drainage
facilities and erosion and sediment control structures should be regularly
inspected and maintained to ensure proper and efficient operation at all
times and particularly following rainstorms. Deposited silt and grit
should be removed regularly and disposed of by spreading evenly over stable,
vegetated areas; · Measures should
be taken to minimize the ingress of site drainage into excavations. If
the excavation of trenches in wet periods is necessary, they should be dug
and backfilled in short sections wherever practicable. Water pumped out
from trenches or foundation excavations should be discharged into storm
drains via silt removal facilities; · Open stockpiles
of construction materials (for example, aggregates, sand and fill material)
of more than 50m3 should be covered with tarpaulin or similar
fabric during rainstorms. Measures should be taken to prevent the
washing away of construction materials, soil, silt or debris into any
drainage system; · Manholes should
always be adequately covered and temporarily sealed so as to prevent silt,
construction materials or debris being washed into the drainage system and
storm runoff being directed into foul sewers; · Precautions be
taken at any time of year when rainstorms are likely, actions to be taken
when a rainstorm is imminent or forecasted, and actions to be taken during or
after rainstorms are summarized in Appendix A2 of ProPECC PN 2/23.
Particular attention should be paid to the control of silty surface runoff
during storm events, especially for areas located near steep slopes; · All vehicles and
plant should be cleaned before leaving a construction site to ensure no
earth, mud, debris and the like is deposited by them on roads. An
adequately designed and site wheel washing facilities should be provided at
every construction site exit where practicable. Wash-water should have
sand and silt settled out and removed at least on a weekly basis to ensure
the continued efficiency of the process. The section of access road
leading to, and exiting from, the wheel wash bay to the public road should be
paved with sufficient backfall toward the wheel wash bay to prevent vehicle
tracking of soil and silty water to public roads and drains; · Oil interceptors
should be provided in the drainage system downstream of any oil/ fuel
pollution sources. The oil interceptors should be emptied and cleaned
regularly to prevent the release of oil and grease into the storm water
drainage system after accidental spillage. A bypass should be provided
for the oil interceptors to prevent flushing during heavy rain; · Construction
solid waste, debris and rubbish on site should be collected, handled and
disposed of properly to avoid water quality impacts; · All fuel tanks
and storage areas should be provided with locks and sited on sealed areas,
within bunds of a capacity equal to 110% of the storage capacity of the
largest tank to prevent spilled fuel oils from reaching water sensitive
receivers nearby; · Adopt best
management practices; · All earth works
should be conducted sequentially to limit the amount of construction runoff
generated from exposed areas during the wet season (April to September) as
far as practicable. |
To minimize water quality impact from the construction site runoff and
general construction activities |
Contractor |
All construction sites where practicable |
Construction stage |
· Water Pollution
Control Ordinance · ProPECC PN 2/23 · TM-EIAO · TM-DSS |
Implemented for the 1st, 3rd, 6th to
10th, 13th, 16th to 17th bullets N/A for other bullets |
|
|
S6.9.1.2 |
W2 |
Tunnelling
Works and Underground Works · Cut-&-cover
tunnelling work should be conducted sequentially to limit the amount of construction
runoff generated from exposed areas during the wet season (April to
September) as far as practicable. · Uncontaminated
discharge should pass through sedimentation tanks prior to off-site
discharge; · The wastewater
with a high concentration of SS should be treated (e.g. by sedimentation
tanks with sufficient retention time) before discharge. Oil
interceptors would also be required to remove oil, lubricants and grease from
the wastewater; · Direct discharge
of the bentonite slurry (as a result of D-wall) is not allowed. It
should be reconditioned and reused wherever practicable. Temporary
storage locations (typically a properly closed warehouse) should be provided
on site for any unused bentonite that needs to be transported away after all
the related construction activities area completed. The requirements in
ProPECC PN 2/23 should be adhered to in the handling and disposal of
bentonite slurries. |
To minimize construction water quality impact from tunnelling works |
Contractor |
All tunnelling portion |
Construction stage |
· Water Pollution
Control Ordinance · ProPECC PN 2/23 · TM-DSS · TM-EIAO |
N/A |
|
|
S6.9.1.3 |
W3 |
Sewage
Effluent · Portable
chemical toilets and sewage holding tanks are recommended for handling the
construction sewage generated by the workforce. A licensed contractor
should be employed to provide appropriate and adequate portable toilets and
be responsible for appropriate disposal and maintenance. |
To minimize water quality from sewage effluent |
Contractor |
All construction sites where practicable |
Construction stage |
· Water Pollution
Control Ordinance · TM-DSS |
Implemented |
|
|
S6.9.1.5 |
W4 |
Groundwater
from Potential Contaminated Area: · No direct
discharge of groundwater from contaminated areas should be adopted. · A discharge
license under the WPCO through the Regional Office of EPD for groundwater
discharge should be applied. Prior to the excavation works within these
potentially contaminated areas, the groundwater quality should be reviewed
during the process of discharge license application. The compliance to the
Technical Memorandum on Standards for Effluents Discharged into Drainage on
Sewerage Systems, Inland and Coastal Waters (TM-DSS) and the existence of
prohibited substance should be confirmed. If the review results indicated
that the groundwater to be generated from the excavation works would be
contaminated, the contaminated groundwater should be either properly treated
in compliance with the requirements of the TM-DSS or properly recharged into
the ground. · If wastewater
treatment is deployed, the wastewater treatment unit shall deploy suitable
treatment process (e.g. oil interceptor / activated carbon) to reduce the
pollution level to an acceptable standard and remove any prohibited
substances (e.g. TPH) to undetectable range. All treated effluent from
wastewater treatment plant shall meet the requirements as stated in TM-DSS
and should be discharged into the foul sewers. · If groundwater
recharging wells are deployed, recharging wells should be installed as
appropriate for recharging the contaminated groundwater back into the ground.
The recharging wells should be selected at places where the groundwater
quality will not be affected by the recharge operation as indicated in the
Section 2.3 of TM-DSS. The baseline groundwater quality shall be determined
prior to the selection of the recharge wells, and submit a working plan
(including the laboratory analytical results showing the quality of
groundwater at the proposed recharge location(s) as well as the pollutant
levels of groundwater to be recharged) to EPD for agreement. Pollution levels
of groundwater to be recharged shall not be higher than pollutant levels of
ambient groundwater at the recharge well. Prior to recharge, any prohibited
substances such as TPH products should be removed as necessary by installing the
petrol interceptor. |
To minimize groundwater quality impact from contaminated area |
Contractor |
Excavation areas where contamination is found |
Construction stage |
· Water Pollution
Control Ordinance · TM-DSS · TM-EIAO |
N/A |
|
|
S6.9.1.6 |
W6 |
Accidental
Spillage In
order to prevent accidental spillage of chemicals, the following is
recommended: · All
the tanks, containers, storage area should be bunded and the locations should
be locked as far as possible from the sensitive watercourse and stormwater
drains; · The
Contractor should register as a chemical waste producer if chemical wastes
would be generated. Storage of chemical waste arising from the
construction activities should be stored with suitable labels and warnings. Disposal
of chemical wastes should be conducted in compliance with the requirements as
stated in the Waste Disposal (Chemical Waste) (General) Regulation. |
To minimize water quality impact from accidental spillage |
Contractor |
All construction site where practicable |
Construction stage |
· Water Pollution
Control Ordinance · ProPECC PN 2/23 · TM-EIAO · TM-DSS |
Implemented, rectified after observation for the 1st
bullet. |
|
|
Waste Management (Construction Waste) |
|||||||||
|
S7.4.1 |
WM1 |
On-site
sorting of C&D material · Geological
assessment should be carried out by competent persons on site during
excavation to identify materials which are not suitable to use as aggregate
in structural concrete (e.g. volcanic rock, Aplite dyke rock, etc.).
Volcanic rock and Aplite dyke rock should be separated at the source sites as
far as practicable and stored at designated stockpile area preventing them
from delivering to crushing facilities. The crushing plant operator
should also be reminded to set up measures to prevent unsuitable rock from
ending up at concrete batching plants and be turned into concrete for
structural use. Details regarding control measures at source site and
crushing facilities should be submitted by the Contractor for the Engineer to
review and agree. In addition, site records should also be kept for the
types of rock materials excavated and the traceability of delivery will be
ensured with the implementation of Trip Ticket System and enforced by site
supervisory staff as stipulated under DEVB TC(W) No. 6/2010 for tracking of
the correct delivery to the rock crushing facilities for processing into
aggregates. Alternative disposal option for the reuse of volcanic rock
and Aplite Dyke rock, etc. should be explored. |
Separation of unsuitable rock from ending up at concrete batching
plants and be turned into concrete for structural use |
Contractor |
All construction sites |
Construction stage |
· DEVB (W) No.
6/2010 |
N/A |
|
|
S7.5.1 |
WM2 |
Construction
and Demolition Material · Maintain
temporary stockpiles and reuse excavated fill material for backfilling and
reinstatement; · Carry
out on-site sorting; · Make
provisions in the Contract documents to allow and promote the use of recycled
aggregates where appropriate; · Adopt
‘selective demolition’ technique to demolish the existing structures and
facilities with a view to recovering broken concrete effectively for
recycling purpose, where possible; · Implement
a trip-ticket system for each works contract to ensure that the disposal of
C&D materials is properly documented and verified; and · Implement
an enhanced Waste Management Plan similar to ETWBTC (Works) No. 19/2005 –
“Environmental Management on Construction Sites” to encourage on-site sorting
of C&D materials and to minimize their generation during the course of
construction. |
Good site practice to minimize the waste generation and recycle the
C&D materials as far as practicable so as to reduce the amount for final
disposal |
Contractor |
All construction sites |
Construction stage |
· Land
(Miscellaneous Provisions) Ordinance · Waste Disposal
Ordinance · ETWB TCW No.
19/2005 |
Implemented for the 1st, 2nd, 5th, 6th
bullets N/A for other bullets |
|
|
S7.5.1 |
WM3 |
C&D
Waste · Standard
formwork or pre-fabrication should be used as far as practicable in order to
minimize the arising of C&D materials. The use of more durable
formwork or plastic facing for the construction works should be
considered. Use of wooden hoardings should not be used, as in other
projects. Metal hoarding should be used to enhance the possibility of
recycling. The purchasing of construction materials will be carefully
planned in order to avoid over ordering and wastage; · The
Contractor should recycle as much of the C&D materials as possible
on-site. Public fill and C&D waste should be segregated and stored in
different containers or skips to enhance reuse or recycling of materials and
their proper disposal. Where practicable, concrete and masonry can be
crushed and used as fill. Steel reinforcement bar can be used by scrap
steel mills. Different areas of the sites should be considered for such
segregation and storage. |
Good site practice to minimize the waste generation and recycle the
C&D materials as far as practicable so as to reduce the amount for final
disposal |
Contractor |
All construction sites |
Construction stage |
· Land
(Miscellaneous Provisions) Ordinance · Waste Disposal
Ordinance · ETWB TCW No.
19/2005 |
N/A |
|
|
S7.5.1 |
WM4 |
Excavated
Contaminated Soils · Details
of the mitigation measures on handling of the contaminated soil shall be
referred to Section on Land Contamination below. |
The contaminated soil will be excavated for on-site reuse |
Contractor |
PBH4 |
Prior to commencement of construction works within the contaminated area |
· Practice Guide
(PG) for Investigation and Remediation of Contaminated Land · GN/GM for land
contamination |
N/A |
|
|
S7.5.1 |
WM5 |
Land-based
Sediment · All
construction plant and equipment shall be designed and maintained to minimize
the risk of silt, sediments, contaminants or other pollutants being released
into the water column or deposited in the locations other than designated
location; · All
vessels shall be sized such that adequate draft is maintained between vessels
and the sea bed at all states of the tide to ensure that undue turbidity is
not generated by turbulence from vessel movement or propeller wash; · Before
moving the vessels which are used for transporting dredged material, excess
material shall be cleaned from the decks and exposed fittings of vessels and
the excess materials shall never be dumped into the sea except at the
approved locations; · Adequate
freeboard shall be maintained on barges to ensure that decks are not washed
by wave action. · The
Contractors shall monitor all vessels transporting material to ensure that no
dumping outside the approved location takes place. The Contractor shall keep
and produce logs and other records to demonstrate compliance and that
journeys are consistent with designated locations and copies of such records
shall be submitted to the engineers; · The
Contractors shall comply with the conditions in the dumping license. · All
bottom dumping vessels (Hopper barges) shall be fitted with tight fittings
seals to their bottom openings to prevent leakage of material; · The
material shall be placed into the disposal pit by bottom dumping; · Contaminated
marine mud shall be transported by spit barge of not less than 750m3
capacity and capable of rapid opening and discharge at the disposal site; · Discharge
shall be undertaken rapidly, and the hoppers shall be closed immediately.
Material adhering to the sides of the hopper shall not be washed out of the
hopper and the hopper shall remain closed until the barge returns to the
disposal site. · For
Type 3 special disposal treatment, sealing of contaminant with geosynthetic
containment before dropping designated mud pit would be a possible
arrangement. A geosynthetic containment method is a method whereby the
sediments are sealed in geosynthetic containers and, the containers would be
dropped into the designated contaminated mud pit where they would be covered
by further mud disposal and later by the mud pit capping at the disposal
site, thereby fulfilling the requirements for fully confined mud disposal. |
To control pollution due to marine sediment |
Contractor |
Along CKR alignment |
Construction stage |
· ETWB TCW No.
34/2002 |
N/A |
|
|
S7.5.1 |
WM6 |
Chemical
Waste · Chemical waste
that is produced, as defined by Schedule 1 of the Waste Disposal (Chemical
Waste) (General) Regulation, should be handled in accordance with the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes; · Containers used
for the storage of chemical wastes should be suitable for the substance they
are holding, resistant to corrosion, maintained in a good condition, and
securely closed, have a capacity of less than 450 L unless the specification
has been approved by EPD, and display a label in English and Chinese in
accordance with instructions prescribed in Schedule 2 of the regulation; · The storage area
for chemical wastes should be clearly labelled and used solely for the
storage of chemical waste, enclosed on at least 3 sides, have an impermeable
floor and bunding of sufficient capacity to accommodate 110% of the volume of
the largest container or 20% of the total volume of waste stored in that
area, whichever is the greatest, have adequate ventilation, covered to
prevent rainfall entering, and arranged so that incompatible materials are
adequately separated; · Disposal of
chemical waste should be via a licensed waste collector, be to a facility
licensed to receive chemical waste, such as the Chemical Waste Treatment
Centre which also offers a chemical waste collection service and can supply
the necessary storage containers, or be to a reuser of the waste, under
approval from EPD. |
Control the chemical waste and ensure proper storage, handling and
disposal |
Contractor |
All construction sites |
Construction stage |
· Waste Disposal
(Chemical Waste) (General) Regulation · Code of Practice
on the Packaging, Labelling and Storage of Chemical Waste |
Implemented for the 2nd, 3rd bullets. N/A for other bullets. |
|
|
S7.5.1 |
WM7 |
General
Refuse · General refuse
generated on-site should be stored in enclosed bins or compaction units
separately from construction and chemical wastes; · A reputable waste
collector should be employed by the Contractor to remove general refuse from
the site, separately from construction and chemical wastes, on a daily basis
to minimize odour, pest and litter impacts. Burning of refuse on
construction sites is prohibited by law. · Aluminium cans
are often recovered from the waste stream by individual collectors if they
are segregated and made easily accessible. Separate labelled bins for
their deposit should be provided if feasible; · Office wastes can
be reduced through the recycling of paper if volumes are large enough to
warrant collection. Participation in a local collection scheme should
be considered by the Contractor. |
Minimize production of the general refuse and avoid odour, pest and
litter impacts |
Contractor |
All construction sites |
Construction stage |
· Waste Disposal
Ordinance |
Implemented |
|
|
Hazard to Life |
|||||||||
|
H8 |
The
driver and his assistant should be physically healthy, experienced and have
good safe driving records. The driver should hold a proper driving
licence for the approved transport truck. Dedicated training programme
and regular road safety briefing sessions/ workshops should be provided to
enhance their safe driving attitude and practice. Smoking should be
strictly prohibited. |
To reduce the
risk during explosives transport |
Contractor |
Works areas at
which explosives would be used |
Construction
stage |
- |
N/A |
||
|
S9.18 |
H9 |
Emergency
response plans in case of road accident should be prepared and
implemented. The driver and his assistant should be familiar with the
emergency procedures including evacuation, and proper communication/
fire-fighting equipment should be provided to the driver and his assistant. |
To reduce the
risk during explosives transport |
Contractor |
Works areas at
which explosives would be used |
Construction
stage |
- |
N/A |
|
|
Landscape
& Visual |
|||||||||
|
S10.10.1
Table 10.11 |
LV3 |
Good Site Management · Large temporary
stockpiles of excavated material shall be covered with unobtrusive sheeting
to prevent dust and dirt spreading to adjacent landscape areas and
vegetation, and to create a neat and tidy visual appearance. · Construction
plant and building material shall be orderly and carefully stored in order to
create a neat and tidy visual appearance. |
Minimize visual
impact |
Contractor |
Within Project
site |
Construction
stage |
- |
Implemented for the 2nd bullet N/A for other bullet |
|
|
LV4 |
Screen Hoarding · Decorative screen
hoarding should be erected to screen the public from the construction
area. It should be designed to be compatible with the existing urban
context. |
Minimize visual
impact |
Contractor |
Within Project
site |
Construction
stage |
- |
Implemented |
||
|
S10.10.1
Table 10.11 |
LV5 |
Lighting Control during Construction · All lighting in
the construction site shall be carefully controlled to minimize light
pollution and night-time glare to nearby residencies and GIC. The
Contractor shall consider other security measures, which shall minimize the
visual impacts. |
Minimize visual
impact |
Contractor |
Within Project
site |
Construction
stage |
- |
Implemented |
|
|
S10.10.1
Table 10.11 |
LV6 |
Erosion Control · The potential for
soil erosion shall be reduced by minimizing the extent of vegetation
disturbance on site and by providing a protective cover over newly exposed
soil. |
Minimize landscape impact |
Contractor |
Within Project site |
Construction stage |
- |
Implemented |
|
|
S10.10.1
Table 10.11 |
LV7 |
Tree Protection & Preservation · Carefully
protected during construction. Tree protection measures will be
detailed at the Tree Removal Application stage and plans submitted to the
relevant Government Department for approval in due course in accordance with
ETWB TC No. 3/2006. |
Minimize landscape and visual impact |
Contractor |
Within Project site |
Construction stage |
· ‘Guidelines for
Tree Risk Management and Assessment Arrangement on an Area Basis and on a
Tree Basis’, Greening, Landscape and Tree Management (GLTM) Section, DEVB · Latest
recommended horticultural practices from GLTM Section, DEVB |
Implemented |
|
|
S10.10.1
Table 10.11 |
LV8 |
Tree Transplantation · For trees
unavoidably affected by the Project that have to be removed, where practical
transplantation will be chosen as the top priority method of removal.
If this is not possible or practical compensatory planting will be provided
for trees unavoidably felled (See LV10). For trees unavoidably affected
by the Project works that are transplanted, transplantation must be carried
out in accordance with ETWB TCW 2/2004 and 3/2006. |
Minimize landscape and visual impact |
Contractor |
Within Project site and designated off-site locations |
Prior to Construction stage |
· ETWB TCW 3/2006 · Latest
recommended horticultural practices from Greening, Landscape and Tree
Management (GLTM) Section, DEVB · ETWB TCW 2/2004 |
Implemented |
|
|
S10.10.1
Table 10.11 |
LV9 |
Compensatory Planting · For trees
unavoidably affected by the Project that have to be removed, where practical
transportation will be chosen as the top priority method of removal but if
this is not possible or practical compensatory planting will be provided for
trees unavoidably felled. All felled trees shall be compensated for by
planting trees to the satisfaction of relevant Government projects.
Required numbers and locations of compensatory trees shall be determined and
agreed separately with Government during the Tree Felling Application process
under ETWB TC 3/2006. · Compensatory tree
planting may be incorporated into public open spaces and along roadside
amenity areas affected by the construction works and therefore be part of the
bigger wider planting plans. Onsite compensation planting is preferred
but, if necessary, additional receptor sites outside the Works Area shall be
agreed separately with the Government during the Tree Felling Application
process. |
Minimize visual impact and also enhance landscape |
Contractor |
Within Project site |
Construction stage |
· ETWB TCW 3/2006 · Latest
recommended horticultural practices from Greening, Landscape and Tree
Management (GLTM) Section, DEVB · ETWB TCW 2/2004 |
Implemented |
|
|
S10.10.1 Table 10.11 |
LV10 |
Screen Planting · Tall
screen/buffer trees, shrubs and climbers should be planted, in so far as is
possible, to soften and screen proposed structures such as roads and central
strip, vertical edges and buildings and to enhance streetscape greening
effect where appropriate. Indiscriminate use of trees for screening must be
avoided and the principle of ‘right tree for the right place’ must be
followed. This detail will be provided at the Detailed Design stage. This
measure may additionally form part of the compensatory planting and will
improve and create a pleasant pedestrian environment. |
Minimize visual impact and also enhance landscape. |
Contractor |
Within Project Site |
Construction Phase |
· Guidelines on
Greening of Noise Barriers, issued April 2012, GLTMS, DevB · ETWB TCW 2/2004 |
N/A |
|
|
S10.10.1 Table 10.11 |
LV12 |
Reinstatement · All works areas,
excavated areas and disturbed areas for tunnel construction and temporary
road diversion or any other proposed works shall be reinstated to former
conditions or better, with reasonable landscape treatment and to the
satisfaction of the relevant Government departments. (Specific mitigation for
disturbance to public open space is detailed separately under LV14.) |
Minimize
landscape impact |
Contractor |
Within Project Site |
Construction Phase |
· N/A |
N/A |
|
|
Cultural Heritage Impact (Construction Phase) |
|||||||||
|
S11.4.4 |
CH1 |
The contractor should be alerted during the
construction on the possibility of locating archaeological remains and as a
precautionary measure, AMO shall be informed immediately in case of discovery
of antiquities or supposed antiquities in the subject sites. |
To preserve any
cultural heritage items which may be removed and damaged by the excavation |
Contractor |
During
construction works for cut and cover tunnels |
Construction
stage |
· AMOs requirements |
N/A |
|
|
EM&A
Project |
|||||||||
|
S13.2 |
EM1 |
An Independent Environmental Checker needs to be
employed as per the EM&A Manual |
Control EM&A
Performance |
Highways
Department |
All construction
sites |
Construction
stage |
· EIAO Guidance
Note No. 4/2010 · TM-EIAO |
Implemented |
|
|
S13.2-13.4 |
EM2 |
· An Environmental
Team needs to be employed as per the EM&A Manual; · Prepare a
systematic Environmental Management Plan to ensure effective implementation
of the mitigation measures; · An environmental
impact monitoring needs to be implemented by the Environmental Team to ensure
all the requirements given in the EM&A Manual are fully complied with. |
Perform
environmental monitoring & auditing |
Highways
Department/ Contractor |
All construction
sites |
Construction
stage |
· EIAO Guidance
Note No. 4/2010 · TM-EIAO |
Implemented |
|
Appendix
G
Waste
Flow Table
Appendix
H
Statistics
on Complaint, Notifications of Summons and Successful Prosecution
Statistical
Summary of Environmental Complaints
|
Reporting
Period |
Environmental
Complaint Statistics |
||
|
Frequency
|
Cumulative |
Complaint
Nature |
|
|
1
September 2026 - 30
September 2026 |
0 |
4 |
N/A |
Statistical
Summary of Environmental Non-compliance
|
Reporting
Period |
Environmental
Non-compliance Statistics |
||
|
Frequency
|
Cumulative |
Details |
|
|
1
September 2026 - 30
September 2026 |
0 |
0 |
N/A |
Statistical
Summary of Environmental Summons
|
Reporting
Period |
Environmental
Summons Statistics |
||
|
Frequency
|
Cumulative |
Details |
|
|
1
September 2026 - 30
September 2026 |
0 |
0 |
N/A |
Statistical
Summary of Environmental Prosecution
|
Reporting
Period |
Environmental
Prosecution Statistics |
||
|
Frequency
|
Cumulative |
Details |
|
|
1
September 2026 - 30
September 2026 |
0 |
0 |
N/A |